star-fst-l AT lists.bnl.gov
Subject: Star-fst-l mailing list
List archive
Re: [Star-fst-l] Notes from review and action items
- From: nie <nie AT rcf.rhic.bnl.gov>
- To: Gerard Visser <gvisser AT indiana.edu>
- Cc: star-fst-l AT lists.bnl.gov
- Subject: Re: [Star-fst-l] Notes from review and action items
- Date: Wed, 05 Aug 2020 10:58:27 +0800
Hi Zhenyu,
I think we all agree to move the capacitor to the other side at current stage.
Can you provide more information about the conflict? Like top layer or bottom layer?
These information will be helpful for us.
Thanks,
Maowu
在 2020-08-04 23:55,Gerard Visser 写道:
hi Zhenyu,
A few comments below. Thanks,
Gerard
On 8/4/2020 11:48 AM, Ye, Zhenyu wrote:
Dear all,
I think the review went smoothly yesterday. Thanks for all the hard work. I think we were able to answer most of the questions from the committee and also received very helpful suggestions from them. The committee is now working on the report, which will be distributed later this week.
Below are some notes I took from the review. Please feel free to comment or add.
*************************************
Mechanical structure:
Use thermal camera with cooling applied to the other side of the mechanical structure to check if there is air trapped between hybrid and MS
We may expect there will be air pockets. What is the action to take?
Are we expecting to develop some criteria on where there must not be
air pockets, or on size of air pockets?
Add an explicit step in the document/traveller to clean the flux after components mounting on the hybrid
Add details about criteria of acceptance/rejection into traveller
Send bare modules to US as soon as they are produced and certified
T-board:
Check the updated T-board design as soon as new T-boards are produced
Also, see below.
Module assembly/test at FNAL/UIC:
Find a better (clear) way to present the efficiency and clarify the KPP requirements
Optimize the production plan to create float: have two production lines, start module assembly with APV chips when the bare modules are available
Mechanical integration:
Find out the flatness requirement for mounting modules onto the support structure?
Define the tolerance requirement for installation and survey
Ground the cooling tube and supporting structure
We should probably do this by a local connection to the T-board. Let's
identify a suitable way and add this possibility in T-board revision
which is happening anyway now. It was done similarly on IST I believe
(actually on hybrid there but T-board more appropriate here in FST I
think, certainly because the hybrid designs should be considered
frozen now.
Add handles and pieces to the installation tooling to make it easier to grab if needed during installation_______________________________________________
*************************************
Below I also list the action items from previous weeks, as well some new ones which appear from the discussions in the last few weeks
*************************************
1) Design and fabricate light-tight box for the DAQ integration test at BNL - Rahul/Flemming
2) Design the cooling lines, and cable trays between disks and cooling manifold - Felix/Rahul
3) Finalize how to mount modules onto the half-rings, and half-rings onto support structure, and document the proposed changes to the mechanical structure - Rahul/Yi/Zhenyu
4) Design and fabricate module storage boxes for production at UIC - Xu/Andres
5) Duplicate the module assembly tooling at UIC - Xu/Zhenyu
6) Update the T-board design to avoid the conflict with Mechanical structure - Jianing
7) Look into the possibility to split the inner and outer sensor HV bias - Mike/Gerard/Jianing
8) Send the problematic prototype cable-T-board assembly to Mike for investigation - Zhenyu/Mike
9) Develop the QC procedure for Inner cable and T-board assembly - Mike/Maowu
10) Look into the overall large CMN noise, and the abnormal noise of few channels first appear in the readout - Gerard/Xu
11) Check the FST noise performance at high readout rate - Xu/Zhenyu
12) Sett up the laser test stand to characterize prototype module performance - Andres/Zhenyu
13) FST slow simulator with efficiency/resolution measured with prototypes and study tracking performance - Gavin/Shenghui
*************************************
Let’s discuss about all these at the FST meeting next Monday. Hopefully we will have the committee’s report by then.
https://drupal.star.bnl.gov/STAR/event/2020/08/10/star-forward-silicon-tracker-meeting
Best,
Zhenyu
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
[Star-fst-l] Notes from review and action items,
Ye, Zhenyu, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
Gerard Visser, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
Ye, Zhenyu, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
Gerard Visser, 08/05/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/06/2020
- Re: [Star-fst-l] Notes from review and action items, Gerard Visser, 08/06/2020
- Re: [Star-fst-l] Notes from review and action items, nie, 08/06/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/06/2020
-
Re: [Star-fst-l] Notes from review and action items,
Gerard Visser, 08/05/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
Ye, Zhenyu, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
nie, 08/04/2020
-
Re: [Star-fst-l] Notes from review and action items,
Gerard Visser, 08/04/2020
Archive powered by MHonArc 2.6.24.