Hi Gerard and Mike,

This reminds we need to check before installation all the grey cables we want to use.
Of the two grey cables we pulled on the south platform one had a connector issues.
We should device a proper testing plan with setup for the grey cable in physics and then start doing testing as filler job in the next few months. TSimilar testing should be done for the purple cables once we start producing them.

Best Flemming


On 2021-02-15 14:06, Visser, Gerard wrote:
Hi Xu,
Ok, thanks for clarifying. I have no theory what is going on. I
hope that we don't see this problem on more cables.
Mike, I guess we should hi-pot the lines used for bias, to all
other lines. 200 VDC is probably a good test voltage. Current limiting
certainly should be done for such a test (10 uA or so is good. maybe
use one of them NIM wire chamber PS modules, if can be set to such a
low voltage? I am not sure.)
Or maybe we can hope you see something on visual inspection.

Gerard

-------------------------

From: Xu Sun <sunxuhit AT gmail.com>
Sent: Monday, February 15, 2021 1:33 PM
To: Visser, Gerard <gvisser AT indiana.edu>
Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: Re: [Star-fst-l] Weekly FST meeting, Feb 15 8:30am (BNL time)


Hi Gerard,

So, after a little while power off, you reconnected GC26, saw no
issue at first (??) then set inner HV to 140 V and then there was this
noise issue and it remains after no matter what the HV is set to?
This one is what I observed.

Best,

Xu

On Mon, Feb 15, 2021 at 12:31 PM Visser, Gerard <gvisser AT indiana.edu>
wrote:

hi Xu,
So, after a little while power off, you reconnected GC26, saw no
issue at first (??) then set inner HV to 140 V and then there was
this noise issue and it remains after no matter what the HV is set
to?
Or, after a little while power off, you reconnected GC26 and
immediately saw the issue, no matter what the HV is set to?
Sorry to be pedantic but there is something strange with this
problem and we may need more clues.
Thanks
Gerard

-------------------------

From: Xu Sun <sunxuhit AT gmail.com>
Sent: Monday, February 15, 2021 1:10 PM
To: Visser, Gerard <gvisser AT indiana.edu>
Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: Re: [Star-fst-l] Weekly FST meeting, Feb 15 8:30am (BNL
time)

Hi Gerard,

Did you guys power cycle the readout system after the mysterious
noise appeared with GC26?
Yes, we have done it multiple times before we switch to GC13.

I wonder if power cycling might have fixed it or it was definitely
confirmed to be the cable GC26, e.g. you put that one back again and
problem appeared again even w/o bias?
To confirm the issue, I just re-connected the GC26 again, and the
issue appeared again. It will appear after inner HV ramp to 140V and
stays there no matter what the HV is.

On the T board fitting - is it going to be possible to fasten the
T board to mechanical structure with screws and nuts?
I believe it is possible to do that with proper nuts. But I don't
know what kind of nuts will be proper. And the outer hybrid will be
bend slightly since the T-board will be attached to the MS through
the nuts.

Best,

Xu

On Mon, Feb 15, 2021 at 10:36 AM Visser, Gerard
<gvisser AT indiana.edu> wrote:

hi Xu,
Did you guys power cycle the readout system after the mysterious
noise appeared with GC26? (I assume it was power cycled in the
changing to GC13. I wonder if power cycling might have fixed it or
it was definitely confirmed to be the cable GC26, e.g. you put that
one back again and problem appeared again even w/o bias?

I can't recall that we ever had such a problem before. Please
inspect the pins on the connectors, though I guess you already have
done that and would have mentioned if one looked damaged.

On the T board fitting - is it going to be possible to fasten
the T board to mechanical structure with screws and nuts? If not,
I'm a little worried that moving the cable around as things get
installed may flex something and cause troubles.

- Gerard

-------------------------

From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> on behalf of Xu
Sun <sunxuhit AT gmail.com>
Sent: Monday, February 15, 2021 11:12 AM
To: Capotosto, Michael <capotosto AT bnl.gov>
Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: Re: [Star-fst-l] Weekly FST meeting, Feb 15 8:30am (BNL
time)

Hi Mike,

My slides can be found in the following link:

https://drupal.star.bnl.gov/STAR/system/files/FstModuleAssemblyFeb08Feb142021.pdf

We will need your help on the new purple cable test shown in slide 3
and gray cable issue discussed in slide 5.
Please let us know your comments.

Best,

Xu

On Sun, Feb 14, 2021 at 11:07 PM Capotosto, Michael
<capotosto AT bnl.gov> wrote:
Hey Zhenyu, all,

Monday is a lab holiday so you may be short some people.

--Mike

-----Original Message-----
From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> On Behalf Of Ye,
Zhenyu
Sent: Sunday, February 14, 2021 7:30 PM
To: Star-fst L <star-fst-l AT lists.bnl.gov>
Subject: [Star-fst-l] Weekly FST meeting, Feb 15 8:30am (BNL time)

Dear all,

We will have a weekly FST meeting tomorrow starting at 8:30am EST
(BNL local time).


https://drupal.star.bnl.gov/STAR/event/2021/02/15/star-forward-silicon-tracker-meeting

0. follow-ups on review and action items *
1. Integration
by Rahul Sharma, Felix Archampong
2. Hybrid and T-board
by Maowu Nie, Mike Capotosto
3. Mechanical Structure
by Yi Yang
4. Production module assembly by
Xu Sun/Shenghui Zhang

*

https://drupal.star.bnl.gov/STAR/event/2021/02/15/star-forward-silicon-tracker-meeting/follow-action-items
[1]

Zhenyu

********** ZOOM Meeting ********** **********
ID: 879 0430 2955
Passcode: fSTAR2021
********** ********** ********** ********** *******
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l


Links:
------
[1] https://drupal.star.bnl.gov/STAR/event/2021/02/15/star-forward-silicon-tracker-meeting/follow-action-items
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l

--
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973

phone: 631-344-4106
cell : 631-681-1596




Archive powered by MHonArc 2.6.24.

Top of Page