usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT
- From: "Kotcher, Jonathan" <kotcher AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "David W. Miller" <David.W.Miller AT uchicago.edu>, Stephanie Majewski <smajewsk AT uoregon.edu>
- Cc: Michael Tuts <tuts AT pmtuts.net>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT
- Date: Thu, 12 Dec 2019 21:06:54 +0000
Yes, you either just scale it by some appropriate factor, or add a fraction
of the following year (except there is ramp up by then, etc.)
But these are crayon-level estimates, will have to be accepted when things
are requested on such time scales
Thx --j
On 12/12/19, 4:03 PM, "Usatlas-hllhc-l2deputymgmt-nsf-l on behalf of John
Parsons" <usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov on behalf of
parsons AT nevis.columbia.edu> wrote:
OK, I will take FY21 + 0.5*FY21 as some ballpark estimate, assume we
need ALL the engineering manpower and 50% of the technician manpower,
and nothing else (ie. no M&S or travel or ...). That will give at least
some approximation of what it would take to not lose the people.
On 12/12/19 3:58 PM, David W. Miller wrote:
> Good point, I’d forgotten that. Indeed, should take the full FY20
number
> then indeed.
>
> Thanks!
> David
>
>
>> On Dec 12, 2019, at 2:57 PM, Stephanie Majewski <smajewsk AT uoregon.edu
>> <mailto:smajewsk AT uoregon.edu>> wrote:
>>
>> Hi David,
>>
>> I thought in the cost books FY20 only included MREFC...? So no need to
>> take the 1/2.
>>
>> Stephanie
>>
>> On Thu, Dec 12, 2019 at 12:53 PM David W. Miller
>> <David.W.Miller AT uchicago.edu <mailto:David.W.Miller AT uchicago.edu>>
wrote:
>>
>> Hi John,
>>
>> What I did (in a private mail sent to Mark Oreglia for comment)
>> was just to average FY20 and FY21 since Apr2020—Mar2021 spans half
>> of each.
>>
>> Cheers,
>> David
>>
>> > On Dec 12, 2019, at 2:44 PM, John Parsons
>> <parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>>
>> wrote:
>> >
>> >
>> > Hi all,
>> >
>> > I was looking back at the documentation from the time of
>> FDR, such as the L2 Cost Book. However, everything is rolled up
>> according to FY, so I don't see a simple way with those docs to
>> get the costs for Apr. 1/2020 - Mar. 31/2021.
>> > Mike/Jon, will you be able to get that from the Cost
>> Controls people?
>> >
>> > John
>> >
>> > On 12/12/19 1:14 PM, Michael Tuts wrote:
>> >> Hi NSF scope L2 and deputy,
>> >> Despite knowing the LS3 would be delayed by a year, NSF is now
>> asking on a very short timescale for an assessment of the impact.
>> There is one question posed where we can use your input on the
>> impact of a 1 year delay of MREFC funding.
>> >> “Please also comment on the impacts, by Level 2 WBS, of the
>> impacts if there were to be a one-year delay in the start of MREFC
>> funding. Include the risks or standing army costs of engineer and
>> technician labor, or other negative impacts of NSF funding delay.
>> Im assuming the risk of losing key technical staff in your
>> engineering pool that would otherwise move to other projects at
>> the various universities is a big factor.”
>> >> Can you please provide an initial assessment for your L2 asap –
>> note we are requested to provide an answer by 9am tomorrow
(Friday)!
>> >> Thanks, PO
>> >> *From:* Coles, Mark W. <mcoles AT nsf.gov <mailto:mcoles AT nsf.gov>>
>> >> *Sent:* Thursday, December 12, 2019 12:23 PM
>> >> *To:* Michael Tuts <tuts AT pmtuts.net <mailto:tuts AT pmtuts.net>>;
>> Anders Ryd <anders.ryd AT cornell.edu <mailto:anders.ryd AT cornell.edu>>
>> >> *Cc:* Gonzalez, Saul <sgonzale AT nsf.gov
>> <mailto:sgonzale AT nsf.gov>>; Caldwell, C. Denise <dcaldwel AT nsf.gov
>> <mailto:dcaldwel AT nsf.gov>>
>> >> *Subject:* VERY IMPORTANT
>> >> *Importance:* High
>> >> Dear Mike and Anders
>> >> Would each of you please send me, by 9AM Friday morning, your
>> immediate assessment of the impacts on the ATLAS or CMS MREFC
>> program of the CERN schedule delay? Please provide a summary, by
>> level 2 WBS element, of what you believe this impacts to be, or if
>> there are none.
>> >> Please also comment on the impacts, by Level 2 WBS, of the
>> impacts if there were to be a one-year delay in the start of MREFC
>> funding. Include the risks or standing army costs of engineer and
>> technician labor, or other negative impacts of NSF funding delay.
>> Im assuming the risk of losing key technical staff in your
>> engineering pool that would otherwise move to other projects at
>> the various universities is a big factor.
>> >> Please provide a summary description of the process that ATLAS
>> and CMS, at the international level, will implement (or that you
>> anticipate they will implement) to realign their construction
>> programs, and any knock-on effects on NSF.
>> >> Please try to keep this at a concise summary level so that the
>> whole response is about one page for each detector.
>> >> I expect to get a thousand hand wringing questions from various
>> high officials within NSF about this, as they hate surprises.
>> Obvviously you are having to react quickly to new information, so
>> it will be important to emphasize where the NSF program is
>> decoupled from other agency activities or the international
>> schedule, minimizing impacts, and where a delayed start by NSF
>> would nevertheless be damaging to NSF-supported scientists and
>> their opportunities to participate in the HL LHC program.
>> >> Email if you have more questions. Our goal here at NSF is to
>> put out a three page summary by COB Friday, one page from NSF
>> internal evaluation, one page from ATLAS, and one from CMS.
>> >> The delay information we’ve seen here at NSF was blamed on the
>> need for a long detector fabrication schedule. What is driving it?
>> >> Thanks
>> >> Mark
>> >> _______________________________________________
>> >> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> >> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>> >>
>>
https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!Xev7P0lg11r1uuKZqpmcW-3ngbM0I423yHYW1d8Xc-gz37u_ym5WF8_friwwxsRb8T8$
>>
>> >
>> > --
>> >
>>
______________________________________________________________________
>> >
>> > John Parsons
>> > Nevis Labs, Email: parsons AT nevis.columbia.edu
>> <mailto:parsons AT nevis.columbia.edu>
>> > Columbia University Phone: (914) 591-2820
>> > P.O. Box 137 Fax: (914) 591-8120
>> > Irvington, NY 10533 WWW:
>>
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=Z0wuTxQYnTTMlYma4lGZlO3skeCGVBrGGurYkWbhJsJuG5HaY82rmCNSdFOV7C4Z&m=iGs3hVDY7I8x8431V5EUhE-U8067DiiBCuW0wQcPfNA&s=IVwIexqfUeKKouYh65z7vIsZw2E6e_D-oxa6lK9qwlc&e=
>>
>> >
>> >
>>
______________________________________________________________________
>> > _______________________________________________
>> > Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> > Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>> >
>>
https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!Xev7P0lg11r1uuKZqpmcW-3ngbM0I423yHYW1d8Xc-gz37u_ym5WF8_friwwxsRb8T8$
>>
>>
>> _______________________________________________
>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>>
https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!Xev7P0lg11r1uuKZqpmcW-3ngbM0I423yHYW1d8Xc-gz37u_ym5WF8_friwwxsRb8T8$
>>
>>
>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=Z0wuTxQYnTTMlYma4lGZlO3skeCGVBrGGurYkWbhJsJuG5HaY82rmCNSdFOV7C4Z&m=7W7XV5YqVcU3cM2o6UEwWxMsIDNJu8EwwM0aFYBPF4w&s=AHnjASh-Jz9DMCi0LUGJbqmeotIRy85YR7-tUuwCgWY&e=
______________________________________________________________________
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
Michael Tuts, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
John Parsons, 12/12/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT, Stephanie Majewski, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
David W. Miller, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
Stephanie Majewski, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
David W. Miller, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
John Parsons, 12/12/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT, Kotcher, Jonathan, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
John Parsons, 12/12/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT, David W Miller, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
John Parsons, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
David W. Miller, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
Stephanie Majewski, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: VERY IMPORTANT,
John Parsons, 12/12/2019
Archive powered by MHonArc 2.6.24.