Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: [Usatlas-hllhc-pomgmt-l] First draft at MREFC delay note
- From: Michael Tuts <tuts AT pmtuts.net>
- To: Hal Evans <hgevans AT indiana.edu>, John Parsons <parsons AT nevis.columbia.edu>, "usatlas-hllhc-pomgmt-l AT lists.bnl.gov" <usatlas-hllhc-pomgmt-l AT lists.bnl.gov>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: [Usatlas-hllhc-pomgmt-l] First draft at MREFC delay note
- Date: Fri, 13 Dec 2019 12:00:27 +0000
OK thanks.
-----Original Message-----
From: Hal Evans <hgevans AT indiana.edu>
Sent: Thursday, December 12, 2019 6:27 PM
To: John Parsons <parsons AT nevis.columbia.edu>; Michael Tuts
<tuts AT pmtuts.net>; usatlas-hllhc-pomgmt-l AT lists.bnl.gov;
usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [External] Re: [Usatlas-hllhc-pomgmt-l]
[Usatlas-hllhc-l2deputymgmt-nsf-l] First draft at MREFC delay note
Hi Mike,
This looks good to me. Thanks for putting it together! Only one other small
item: on the second-to-last bullet, I would remove "(even if we were able to
support the standing army costs)". If we were able to fund these people as a
standing army, we wouldn't lose them. I think that we make the point
adequately by just saying "risk the loss of key personnel".
Thanks - Hal
On 12/12/19 6:17 PM, John Parsons wrote:
> This message was sent from a non-IU address. Please exercise caution
> when clicking links or opening attachments from external sources.
> -------
>
> I would suggest to move the last bullet (about the Risk register item)
> up to immediately after the chart, since it follows the logic of
> continuing on the current schedule, but having the end-date stretched
> out. In contrast, The bullets after the chart are about the impact of
> delaying the MREFC funding (ie. NOT continuing on our current
> schedule, but instead putting the project "on hold" for a year).
>
> John
>
> On 12/12/19 4:50 PM, Michael Tuts wrote:
>> Hi
>>
>> Attached is a first draft of the MREFC note to Coles. I have to go
>> offline for a few hours now, but will return this evening late.
>> Comments/changes of course welcome.
>>
>> Mike
>>
>>
>>
>>
>> _______________________________________________
>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf
>> -l
>>
>
--
^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v
Hal Evans hgevans AT indiana.edu
https://urldefense.proofpoint.com/v2/url?u=http-3A__pages.iu.edu_-7Ehgevans_&d=DwIGaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=Z0wuTxQYnTTMlYma4lGZlO3skeCGVBrGGurYkWbhJsJuG5HaY82rmCNSdFOV7C4Z&m=fNVKrwjBxFHxKOv7GxbXFxXSpf-cXRo9Hena2bZAEyw&s=XiJnmlDeykK5vaZSVvB1s9zFQXrbjXmDKFnCw8QquDA&e=
Tel: (812)856-3828 Fax: (812)855-5533
253 Swain Hall West Indiana University
727 E. Third St. Bloomington, IN 47405
v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] First draft at MREFC delay note,
Michael Tuts, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] First draft at MREFC delay note,
John Parsons, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: [Usatlas-hllhc-pomgmt-l] First draft at MREFC delay note,
Hal Evans, 12/12/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: [Usatlas-hllhc-pomgmt-l] First draft at MREFC delay note, Michael Tuts, 12/13/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] First draft at MREFC delay note, Michael Tuts, 12/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: [Usatlas-hllhc-pomgmt-l] First draft at MREFC delay note,
Hal Evans, 12/12/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] First draft at MREFC delay note,
John Parsons, 12/12/2019
Archive powered by MHonArc 2.6.24.