usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay
- From: Michael Tuts <tuts AT pmtuts.net>
- To: John Parsons <parsons AT nevis.columbia.edu>, "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay
- Date: Fri, 13 Dec 2019 16:48:56 +0000
No, Mark already did that in an initial answer to his bosses so that is
implied -- here he wanted some specific examples of what would be impacted,
so purchases like this make that point. He is basically looking for some
ammunition to tell the committee that it is a dumb idea to delay funding by
three months (even if the HL-LHC start is delayed by a year) because we are
ready to go once funding is released - some are in fact 4/1/20 orders being
placed on the day the funding is released. Just further ammunition for him.
-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Friday, December 13, 2019 11:42 AM
To: Michael Tuts <tuts AT pmtuts.net>; usatlas-hllhc-management-l AT lists.bnl.gov;
usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF
request on impact of 3-month delay
Shouldn't you include also the manpower for those 3 months, which is being
used largely to prepare for those M&S purchases? If we are not allowed to
have our people working on the MREFC tasks during those 3 months, we need
other funds to pay them for that time, just like we argued with the 12-month
delay.
John
On 12/13/19 11:30 AM, Michael Tuts wrote:
> Hi All,
>
> There was another request for immediate input on some specific impacts
> of a three-month delay arising from moving the NSB HL-LHC presentation
> from February to May 2020. That means a 3-month delay in the start of
> the MREFC (from 4/1/20 to 7/1/20). I culled through the FDR detailed
> schedules to find all the material tasks during that three month
> period, to provide Mark with specific examples he requested. The
> attached file is that description (totals about $1M in material
> purchases during that period). Let me know if you have any
> comments/corrections, but be quick.
> Mark wants this by 12pm eastern (in thirty minutes from when I write this).
>
> Thanks, Mike
>
>
>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-
> l
>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIFAg&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=Z0wuTxQYnTTMlYma4lGZlO3skeCGVBrGGurYkWbhJsJuG5HaY82rmCNSdFOV7C4Z&m=3dxSF7ptV17qNq51lCQ8PUFQzukKVRCrhW_8l54Kv9g&s=tbcRJVXhvT19SpE-6-0GwWHGKr9iBMQmCZGiX1skV5s&e=
______________________________________________________________________
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay,
Michael Tuts, 12/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay,
John Parsons, 12/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay,
Michael Tuts, 12/13/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay, John Parsons, 12/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay,
Michael Tuts, 12/13/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay,
John Parsons, 12/13/2019