usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Michael Tuts <tuts AT pmtuts.net>
  • To: "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Draft answer to the next NSF request on impact of 3-month delay
  • Date: Fri, 13 Dec 2019 16:30:11 +0000

Hi All,

There was another request for immediate input on some specific impacts of a three-month delay arising from moving the NSB HL-LHC presentation from February to May 2020. That means a 3-month delay in the start of the MREFC (from 4/1/20 to 7/1/20). I culled through the FDR detailed schedules to find all the material tasks during that three month period, to provide Mark with specific examples he requested. The attached file is that description (totals about $1M in material purchases during that period). Let me know if you have any comments/corrections, but be quick. Mark wants this by 12pm eastern (in thirty minutes from when I write this).

Thanks, Mike



Attachment: Material purchases for 3 month period of MREFC.docx
Description: Material purchases for 3 month period of MREFC.docx