  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Comments on April VRs
  • Date: Thu, 20 May 2021 17:15:44 +0200


Hello all,

The April VRs are due. Here are some comments:

*6.4 is missing
*6.4.1: the text is ok (look at 6.5.1 for one that is very good). But you will be carrying $300k in cost variance for the ADC until pre-production...
*6.4.3 is missing

*6.5 is good, two small typos: have => has, and that => than
*6.5.1 is very good
*6.5.3 and .4 are missing

*6.6, 6.6.1 and 6.6.4 are missing
*6.6.5: the impact statement is too long - look at 6.5 for an example. Basically, we just want to know what the impact is, ie how much delay this represents in delivery date. The explanation text should go under explanation, nit under impact.

*6.8, 6.8.2 and 6.8.3 are missing

Thanks,

Gustaaf