Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Comments on April VRs

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Comments on April VRs
  • Date: Wed, 26 May 2021 19:01:41 -0400


Hello all,

Thanks for the updates.

6.4 and 6.4.3 are *still* missing! Now 3 days late, we're running out of time here.

6.5 is good

6.6.1: "The accounting mistake will be fixed when the funds transfer to CERN goes through. " Why? What does this have to do with funds transfers to CERN? We do accruals, so this should have no relation. This is in explicit violation of the PEP. Please make sure this is fixed in the May accruals report.

6.6.3, 4 and 5 are much better, thanks!

6.8 and 6.8.2 are *still* missing! Now 3 days late, we're running out of time here.