Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides
- From: "Novakova, Penka N" <penka AT bnl.gov>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides
- Date: Wed, 9 Jun 2021 11:33:13 +0000
The plots in IPD can be produced for 12 months only so all SPI/CPI and
BCWS/BCWP/ACWP plots will start in June 2020. The idea is to see the trend in
the last few months not since the beginning of the project.
Thanks,
penka
-----Original Message-----
From: Usatlas-hllhc-l2deputymgmt-nsf-l
<usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov> On Behalf Of Gustaaf
Brooijmans
Sent: Wednesday, June 9, 2021 3:20 AM
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value
Indices and % complete slides
Hi,
It would be better to show history starting with April 2020, since that's the
project start....
Best,
Gustaaf
On 6/8/21 9:58 PM, Evans, Harold G. wrote:
> Dear NSF L2s,
>
> Now that we've completed the DR practice talks, there are a couple of
> slides that we'd like to make more regular across the L2 talks.
> Suggestions are given below.
>
> 1. Earned Value Indices slide: we think that the best strategy (except
> for LAr) for this slide is to just include the two earned value
> history plots (for the period May-20 - May-21) at L2 and then also
> show the CPR numbers from the spreadsheet sent out by the PO. Put the
> L3 history plots into the backup. You can see an example of what we're
> proposing on slide 19 of Stephanie's Trigger talk:
> https://indico.bnl.gov/event/12057/
> <https://indico.bnl.gov/event/12057/>
> You could then just mention the main features of the L2 history plots,
> but only discuss the sources of the current schedule and cost
> variances in the non-COVID and COVID variance slides.
>
> 2.For the "% Complete and Work Remaining" slide, we'd suggest to just
> quote the % complet per L3 system from the May CPR and give a very
> brief (one sentence) summary of where you are in the schedule. This
> would just hit the highest point from your technical progress slides.
>
> Let me know if you have any questions or comments about this.
>
> Thanks - Hal
>
> --
>
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides,
Evans, Harold G., 06/08/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides, Novakova, Penka N, 06/08/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides,
Gustaaf Brooijmans, 06/09/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides,
Novakova, Penka N, 06/09/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides, Gustaaf Brooijmans, 06/10/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] format for Earned Value Indices and % complete slides,
Novakova, Penka N, 06/09/2021
Archive powered by MHonArc 2.6.24.