  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May NSF VR reports
  • Date: Mon, 28 Jun 2021 11:11:39 +0200


Hello all,

Thanks for filling the variance reports. A few comments:

-6.4.1: "The cumulative cost variance is due is dominated by COVID-related inefficiencies in the work performed on the ADC and optics development. "
=> aside from the manifest language issue, I don't understand: how does a positive cost variance arise from a work inefficiency? A positive cost variance means work was done with fewer resources than planned, ie the efficiency was higher, not lower than planned. BTW, all of this variance (and more) is at SMU..

Please fix 6.8.2 and 6.8.3, see comments below.

Thx

Gustaaf



On 6/25/21 10:57 AM, Gustaaf Brooijmans wrote:

Hello all,

The May variance reports are overdue:

6.4.1 is still missing

6.6.3 is good

6.8.2: the explanation is mostly about schedule variance, but only a cost variance is requested.  It took me a bit of time to guess at what the explanation for the cost variance is supposed to mean: is it that more new design work than expected is needed for the prototype?  The impact is only about schedule, whereas the variance is required for cost.  Similarly, the corrective action seems to be about schedule (although that's not 100% clear).

6.8.3: Also here, the requested report is for cost, not schedule variance.  The statements on cost are good, so just remove the statements about schedule.

Please revisit 6.8.2 and .3, and get the missing report in asap.

Thanks!

Gustaaf



On 6/22/21 4:37 PM, Gustaaf Brooijmans wrote:

Hello all,

The May variance reports are due:

6.4.1 is missing

6.6.3 is good

6.8.2 and 6.8.3 are missing

Please get the missing reports in asap.

Thanks!

Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l