usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx
- From: Michael Tuts <tuts AT pmtuts.net>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx
- Date: Tue, 28 Sep 2021 21:24:33 +0000
..but you didn't attach the file ...
-----Original Message-----
From: Usatlas-hllhc-l2deputymgmt-nsf-l
<usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov> On Behalf Of Gustaaf
Brooijmans
Sent: Tuesday, September 28, 2021 4:54 PM
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC
Project Status Report.docx
Hi Mike,
Here's an annotated version. Mostly minor fixes of typos, just one big one.
We cannot write "We passed a L0MDT BCP to re-align the baseline schedule with
the working schedule due to increased complexity" in a report! You cannot do
BCPs primarily to align the baseline and working schedules.
Best,
Gustaaf
On 9/27/21 7:27 PM, Michael Tuts wrote:
> Hi All,
>
> Attached is a draft of the August NSF monthly report. There are still
> a few known missing pieces – where you see some numbers in green that
> I should have tomorrow, and I am missing the 6.4.2 variance report
> (there is an empty placeholder for that in the report) so please upload
> that asap.
>
> I will also send the annual report draft out soon.
>
> Comments and corrections are always welcome.
>
> Thanks, PO
>
>
>
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Michael Tuts, 09/27/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Gustaaf Brooijmans, 09/28/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx, Michael Tuts, 09/28/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Michael Tuts, 09/28/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx, Gustaaf Brooijmans, 09/28/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Gustaaf Brooijmans, 09/28/2021
Archive powered by MHonArc 2.6.24.