Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: Michael Tuts <tuts AT pmtuts.net>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx
- Date: Tue, 28 Sep 2021 19:12:36 -0400
Apologies, here it is.
On 9/28/21 5:24 PM, Michael Tuts wrote:
..but you didn't attach the file ...
-----Original Message-----
From: Usatlas-hllhc-l2deputymgmt-nsf-l
<usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov> On Behalf Of Gustaaf
Brooijmans
Sent: Tuesday, September 28, 2021 4:54 PM
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC
Project Status Report.docx
Hi Mike,
Here's an annotated version. Mostly minor fixes of typos, just one big one. We cannot
write "We passed a L0MDT BCP to re-align the baseline schedule with the working
schedule due to increased complexity" in a report! You cannot do BCPs primarily
to align the baseline and working schedules.
Best,
Gustaaf
On 9/27/21 7:27 PM, Michael Tuts wrote:
Hi All,
Attached is a draft of the August NSF monthly report. There are still
a few known missing pieces – where you see some numbers in green that
I should have tomorrow, and I am missing the 6.4.2 variance report
(there is an empty placeholder for that in the report) so please upload that
asap.
I will also send the annual report draft out soon.
Comments and corrections are always welcome.
Thanks, PO
Attachment:
2021-08 ATLAS MREFC Project Status Report-gb.docx
Description: application/vnd.openxmlformats-officedocument.wordprocessingml.document
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Michael Tuts, 09/27/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Gustaaf Brooijmans, 09/28/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx, Michael Tuts, 09/28/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,
Michael Tuts, 09/28/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx, Gustaaf Brooijmans, 09/28/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] DRAFT 2021-08 ATLAS MREFC Project Status Report.docx,