  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments
  • Date: Tue, 26 Oct 2021 14:30:53 +0200


Hello,

Thanks for filing most variance reports. A few comments

-6.4.1: you should also say there was a mistake in statusing. Otherwise the BCP is not allowed!

-6.4.2 is missing

-6.4.3: "Delay is also being caused by the lack of FPGAs to assemble on the French LASP boards," is not true. The easiest is probably to remove that sentence.

-6.5.1 is fine

-6.6, 6.6.1, 6.6.3 are fine

-6.6.4: there is a $237k schedule variance that is not discussed

-6.6.5: "Error in reporting will be address in the September reports. "?

-6.8 is missing

-6.8.2 is fine

-6.8.3: "It is not yet clear if the additional effort will significantly ameliorate the negative SV over time, so there is currently insufficient evidence to amend EAC for WBS 6.8.3." is a little strange as extra effort should lead to making up schedule. I think it's a leftover from when there was a cost variance... maybe just delete?

Best,

Gustaaf