[Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments
- Date: Tue, 26 Oct 2021 14:30:53 +0200
Hello,
Thanks for filing most variance reports. A few comments
-6.4.1: you should also say there was a mistake in statusing. Otherwise the BCP is not allowed!
-6.4.2 is missing
-6.4.3: "Delay is also being caused by the lack of FPGAs to assemble on the French LASP boards," is not true. The easiest is probably to remove that sentence.
-6.5.1 is fine
-6.6, 6.6.1, 6.6.3 are fine
-6.6.4: there is a $237k schedule variance that is not discussed
-6.6.5: "Error in reporting will be address in the September reports. "?
-6.8 is missing
-6.8.2 is fine
-6.8.3: "It is not yet clear if the additional effort will significantly ameliorate the negative SV over time, so there is currently insufficient evidence to amend EAC for WBS 6.8.3." is a little strange as extra effort should lead to making up schedule. I think it's a leftover from when there was a cost variance... maybe just delete?
Best,
Gustaaf
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments,
Gustaaf Brooijmans, 10/26/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments,
Gustaaf Brooijmans, 10/28/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments, Gustaaf Brooijmans, 10/29/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments,
Gustaaf Brooijmans, 10/28/2021
Archive powered by MHonArc 2.6.24.