  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Variance reports comments
  • Date: Thu, 28 Oct 2021 11:30:13 +0200


Hello all,

A quick update:

-6.4.1: you should also say there was a mistake in statusing.  Otherwise the BCP is not allowed!

This still needs to be fixed.


-6.4.2 is missing

-6.4.3: "Delay is also being caused by the lack of FPGAs to assemble on the French LASP boards," is not true.  The easiest is probably to remove that sentence.

Thanks for 6.4.2 and 6.4.3, those look fine.


-6.5.1 is fine

-6.6, 6.6.1, 6.6.3 are fine

-6.6.4: there is a $237k schedule variance that is not discussed

This still needs to get fixed.



-6.6.5: "Error in reporting will be address in the September reports. "?

-6.8 is missing

-6.8.2 is fine

-6.8.3: "It is not yet clear if the additional effort will significantly ameliorate the negative SV over time, so there is currently insufficient evidence to amend EAC for WBS 6.8.3." is a little strange as extra effort should lead to making up schedule.  I think it's a leftover from when there was a cost variance...  maybe just delete?

All good now.

Best,

Gustaaf