usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- Cc: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab
- Date: Sat, 25 Feb 2023 13:22:16 -0500
Hi Gustaaf,
You mention "NSF guidance for MREFCs is that TPC should be between the 70% and 90% CL". Does the same guidance apply to completion date? In any case, do we have from the MC completion dates for less than 90% CL; it might be a natural question to ask what CL we are consistent with at the moment.
I would not say the supply chain risks for LAr are "wrong". For the recent NSF risk review, we decided (as I believe did other subsystems) to keep unchanged the supply chain risks for items that are not yet completed; ie. we did not revisit the "standard" impacts assumed previously for the various types of things, such as PCB fab, PCB assy, ASICs, ... The same was true for the DOE side, where we did not see a float problem coming from this on the MC for CD/2-3. So I was not expecting such a stark problem to appear on the NSF side.
As I mentioned previously, we can (very) soon retire some of these supply chain risks, at which point there is no need to tweak their potential impacts. For some others, it might be time to revisit the "standard" impact assumptions,
I think I will have to add a slide to my L2 talk that proactively addresses these issues. It will likely not deflect the questions that this is going to cause, but at least we will be seen to be tackling them head on.
John
On 2/25/23 12:13 PM, Gustaaf Brooijmans wrote:
Hi John,
We are using all the "standard" impacts proposed across the project for Supply Chain, eg.
up to 4 months delay for PCB fab. The LAr issue being revealed here, with the implication we could need an
extra ~9 months more than we have before the needed-at-CERN dates, is maybe a reflection of the fact these
are (by now) too conservative? Do we really want to show this at DR?? It seems to me it could become the
"dominant issue" of the entire review? And how do we reply when asked "what happens if the
MC is right and you deliver LAr boards 9 months too late"??
Do you think the supply chain risk registers for LAr are wrong? We recently
had an NSF risk workshop… Anyway, we don’t really have a choice I think in
terms of what we show at the DR. It’s too late to change our approach.
I put some text in my slides along the lines of “we might need extra funds
to accelerate production,” I’m happy to hear more creative suggestions. Of
course it’s not a secret for anybody that pixels and strips for both ATLAS
and CMS are in much worse shape.
Given we have not seen this problem before yesterday, we don't currently have
anything prepared to address it. (as requested, I do not even have the MC results in
my L2 talk) By April, I can see quite a few improvements, since the ADC preprod will
be done and the lpGBT production should be done. Also, we should have received the
preprod. PA/S (from DOE scope) by then. So we could "retire" those. All
that would help, but who knows whether it would be enough to get us to 90%CL float. We
could consider changing some of the assumptions. For example, based on recent
experience, I don't think a potential 4-month delay for PCB fab is a serious
possibility anymore. I would be comfortable reducing it to 2 months max.
That’s up to you. I think PCB fab is probably less of an issue now that
China has ended zero-covid. Parts remain an issue, but maybe for FEB2 there
are few things that can go wrong there.
So, bottom line, here are some questions:
- for next week, you are going to show these float results in your plenary talk? And if so, what
are we going to say? Just say this is a current snapshot, discuss the points above, and argue it
will be "better" by April? That still leaves open for discussion whether it will be
"good enough", and the answer is that today we don't know. This seems problematic to
me.
I don’t think we have a choice. Please take a look at my slides. I’m happy
to adjust the text.
- Or, given that all these changes will happen by April, do we choose to NOT
show the MC schedule result next week? Once the DR is over, we could work
with Chris to see where we expect things to stand at the time of the
rebaseline review?
We have to show MC results. Since this is the DR, I don’t think it’s a huge
deal. We just need to think what the recommendation is we’re fishing for.
Is it “revise the LAr risks” or is it “prepare a plan to accelerate
production should this be needed”?
Best,
Gustaaf
John
On 2/24/23 5:34 PM, Gustaaf Brooijmans wrote:
Hi John,
Yes, but it turns out this is all due to supply chain. In the working
summary sheet you’ll see I made some small annotations. Without supply chain
the 438/461 becomes 251/288, so ~90% CL. We didn’t have supply chain risks
at FDR, or at the summer 2021 annula review.
Best,
Gustaaf
On Feb 24, 2023, at 4:48 PM, John Parsons <parsons AT nevis.columbia.edu> wrote:
Hi Gustaaf,
I am surprised that @ 90%CL LAr seems to need about 200 "extra" days (almost a
year) beyond the float we have. What is driving that? We have certainly made a lot of progress
since FDR, and were not in such bad shape back then. We also have more base float now than we
did at FDR, and yet we are "under water"?
John
On 2/24/23 4:39 PM, Gustaaf Brooijmans wrote:
Hello all,
We think we’ve worked the kinks out of all the numbers. In the attached you
will find a for presentation tab, as well as a working tab with a bit more
info on floats, and all the detailed info. Let us know if you see something
weird. The for presentation tab calculates % contingency on the cost-to-go,
which gives a better idea of where we are.
Best,
Chris and Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ASFZCTHF4B-rJmzzmdz24abBZCEAcU7ANW9qIaUxLlsutCSslqRbFXA9-iexwU7hzvkfViSarv-jlKVlGugtXJp1xaXXDM0qYLmQ11cfQ3v6OmmJAMXWdg$
______________________________________________________________________
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ASFZCTHF4B-rJmzzmdz24abBZCEAcU7ANW9qIaUxLlsutCSslqRbFXA9-iexwU7hzvkfViSarv-jlKVlGugtXJp1xaXXDM0qYLmQ11cfQ3v6OmmJAMXWdg$
______________________________________________________________________
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ASFZCTHF4B-rJmzzmdz24abBZCEAcU7ANW9qIaUxLlsutCSslqRbFXA9-iexwU7hzvkfViSarv-jlKVlGugtXJp1xaXXDM0qYLmQ11cfQ3v6OmmJAMXWdg$
______________________________________________________________________
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Gustaaf Brooijmans, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Chris Meyer, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/27/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Chris Meyer, 02/27/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/27/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Thomas Schwarz, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Gustaaf Brooijmans, 02/26/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/24/2023
Archive powered by MHonArc 2.6.24.