usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: John Parsons <parsons AT nevis.columbia.edu>
- Cc: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab
- Date: Sat, 25 Feb 2023 13:53:17 -0500
Hi John,
>
> You mention "NSF guidance for MREFCs is that TPC should be between
> the 70% and 90% CL". Does the same guidance apply to completion date? In
> any case, do we have from the MC completion dates for less than 90% CL; it
> might be a natural question to ask what CL we are consistent with at the
> moment.
Yes, they’re in the sheet. You’re looking for the LAr maturity+risk tab.
>
> I would not say the supply chain risks for LAr are "wrong". For the
> recent NSF risk review, we decided (as I believe did other subsystems) to
> keep unchanged the supply chain risks for items that are not yet completed;
> ie. we did not revisit the "standard" impacts assumed previously for the
> various types of things, such as PCB fab, PCB assy, ASICs, ... The same
> was true for the DOE side, where we did not see a float problem coming from
> this on the MC for CD/2-3. So I was not expecting such a stark problem to
> appear on the NSF side.
The simulation for the DOE review said 400 days, so this is not so far from
what we expected, no?
>
> As I mentioned previously, we can (very) soon retire some of these
> supply chain risks, at which point there is no need to tweak their
> potential impacts. For some others, it might be time to revisit the
> "standard" impact assumptions,
>
> I think I will have to add a slide to my L2 talk that proactively
> addresses these issues. It will likely not deflect the questions that this
> is going to cause, but at least we will be seen to be tackling them head on.
Yes, I agree. But I think we do want to decide what we would like the
recommendation to say as that will change how we address this.
Best,
Gustaaf
>
> John
>
> On 2/25/23 12:13 PM, Gustaaf Brooijmans wrote:
>> Hi John,
>>>
>>>
>>> We are using all the "standard" impacts proposed across the project
>>> for Supply Chain, eg. up to 4 months delay for PCB fab. The LAr issue
>>> being revealed here, with the implication we could need an extra ~9
>>> months more than we have before the needed-at-CERN dates, is maybe a
>>> reflection of the fact these are (by now) too conservative? Do we really
>>> want to show this at DR?? It seems to me it could become the "dominant
>>> issue" of the entire review? And how do we reply when asked "what
>>> happens if the MC is right and you deliver LAr boards 9 months too late"??
>> Do you think the supply chain risk registers for LAr are wrong? We
>> recently had an NSF risk workshop… Anyway, we don’t really have a choice I
>> think in terms of what we show at the DR. It’s too late to change our
>> approach.
>> I put some text in my slides along the lines of “we might need extra
>> funds to accelerate production,” I’m happy to hear more creative
>> suggestions. Of course it’s not a secret for anybody that pixels and
>> strips for both ATLAS and CMS are in much worse shape.
>>>
>>> Given we have not seen this problem before yesterday, we don't
>>> currently have anything prepared to address it. (as requested, I do not
>>> even have the MC results in my L2 talk) By April, I can see quite a few
>>> improvements, since the ADC preprod will be done and the lpGBT production
>>> should be done. Also, we should have received the preprod. PA/S (from
>>> DOE scope) by then. So we could "retire" those. All that would help,
>>> but who knows whether it would be enough to get us to 90%CL float. We
>>> could consider changing some of the assumptions. For example, based on
>>> recent experience, I don't think a potential 4-month delay for PCB fab is
>>> a serious possibility anymore. I would be comfortable reducing it to 2
>>> months max.
>> That’s up to you. I think PCB fab is probably less of an issue now that
>> China has ended zero-covid. Parts remain an issue, but maybe for FEB2
>> there are few things that can go wrong there.
>>>
>>> So, bottom line, here are some questions:
>>>
>>> - for next week, you are going to show these float results in your
>>> plenary talk? And if so, what are we going to say? Just say this is a
>>> current snapshot, discuss the points above, and argue it will be "better"
>>> by April? That still leaves open for discussion whether it will be "good
>>> enough", and the answer is that today we don't know. This seems
>>> problematic to me.
>>>
>> I don’t think we have a choice. Please take a look at my slides. I’m
>> happy to adjust the text.
>>> - Or, given that all these changes will happen by April, do we choose to
>>> NOT show the MC schedule result next week? Once the DR is over, we could
>>> work with Chris to see where we expect things to stand at the time of the
>>> rebaseline review?
>> We have to show MC results. Since this is the DR, I don’t think it’s a
>> huge deal. We just need to think what the recommendation is we’re fishing
>> for. Is it “revise the LAr risks” or is it “prepare a plan to accelerate
>> production should this be needed”?
>> Best,
>> Gustaaf
>>>
>>> John
>>>
>>> On 2/24/23 5:34 PM, Gustaaf Brooijmans wrote:
>>>> Hi John,
>>>> Yes, but it turns out this is all due to supply chain. In the working
>>>> summary sheet you’ll see I made some small annotations. Without supply
>>>> chain the 438/461 becomes 251/288, so ~90% CL. We didn’t have supply
>>>> chain risks at FDR, or at the summer 2021 annula review.
>>>> Best,
>>>> Gustaaf
>>>>> On Feb 24, 2023, at 4:48 PM, John Parsons <parsons AT nevis.columbia.edu>
>>>>> wrote:
>>>>>
>>>>>
>>>>> Hi Gustaaf,
>>>>>
>>>>> I am surprised that @ 90%CL LAr seems to need about 200 "extra" days
>>>>> (almost a year) beyond the float we have. What is driving that? We
>>>>> have certainly made a lot of progress since FDR, and were not in such
>>>>> bad shape back then. We also have more base float now than we did at
>>>>> FDR, and yet we are "under water"?
>>>>>
>>>>> John
>>>>>
>>>>> On 2/24/23 4:39 PM, Gustaaf Brooijmans wrote:
>>>>>> Hello all,
>>>>>> We think we’ve worked the kinks out of all the numbers. In the
>>>>>> attached you will find a for presentation tab, as well as a working
>>>>>> tab with a bit more info on floats, and all the detailed info. Let us
>>>>>> know if you see something weird. The for presentation tab calculates
>>>>>> % contingency on the cost-to-go, which gives a better idea of where we
>>>>>> are.
>>>>>> Best,
>>>>>> Chris and Gustaaf
>>>>>> _______________________________________________
>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>>>>
>>>>> --
>>>>> ______________________________________________________________________
>>>>>
>>>>> John Parsons
>>>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>>>> Columbia University Phone: (914) 591-2820
>>>>> P.O. Box 137 Fax: (914) 591-8120
>>>>> Irvington, NY 10533 WWW:
>>>>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!HBgbH9-tAB8XvzcQbxzWrhxnc1bZWKHl2E1TcTMED93qGUw6TyH54ShoWcgtknTf5tECy9ZeP3uWl9zU4hfEoQq6UzwYr5YO0EZrhjxZHhqj-MFSvQHhXg$
>>>>>
>>>>>
>>>>> ______________________________________________________________________
>>>>>
>>>
>>> --
>>> ______________________________________________________________________
>>>
>>> John Parsons
>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>> Columbia University Phone: (914) 591-2820
>>> P.O. Box 137 Fax: (914) 591-8120
>>> Irvington, NY 10533 WWW:
>>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!HBgbH9-tAB8XvzcQbxzWrhxnc1bZWKHl2E1TcTMED93qGUw6TyH54ShoWcgtknTf5tECy9ZeP3uWl9zU4hfEoQq6UzwYr5YO0EZrhjxZHhqj-MFSvQHhXg$
>>>
>>>
>>> ______________________________________________________________________
>>>
>
> --
> ______________________________________________________________________
>
> John Parsons
> Nevis Labs, Email: parsons AT nevis.columbia.edu
> Columbia University Phone: (914) 591-2820
> P.O. Box 137 Fax: (914) 591-8120
> Irvington, NY 10533 WWW:
> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!HBgbH9-tAB8XvzcQbxzWrhxnc1bZWKHl2E1TcTMED93qGUw6TyH54ShoWcgtknTf5tECy9ZeP3uWl9zU4hfEoQq6UzwYr5YO0EZrhjxZHhqj-MFSvQHhXg$
>
>
> ______________________________________________________________________
>
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Gustaaf Brooijmans, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Chris Meyer, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/27/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Chris Meyer, 02/27/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, John Parsons, 02/27/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Thomas Schwarz, 02/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Gustaaf Brooijmans, 02/26/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab, Thomas Schwarz, 02/26/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/25/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
Gustaaf Brooijmans, 02/24/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab,
John Parsons, 02/24/2023
Archive powered by MHonArc 2.6.24.