usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: John Parsons <parsons AT nevis.columbia.edu>
  • Cc: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Updated contingency sheet with "for presentation" tab
  • Date: Sun, 26 Feb 2023 14:57:59 -0500


Hi John,

A few commenst on this slide:

-there are no “standard estimates of probability” anymore. We never discuss
these anywhere. I would suggest you just remove that sub-bullet.

-these risks don’t quite dominate, but represent a very large need for extra
float

The rest looks fine.

Best,

Gustaaf


> On Feb 26, 2023, at 1:59 PM, John Parsons <parsons AT nevis.columbia.edu>
> wrote:
>
>
> Here is a screenshot of the slide I added to my L2 talk. Comments welcome.
>
> John
>
> On 2/25/23 1:22 PM, John Parsons wrote:
>> Hi Gustaaf,
>> You mention "NSF guidance for MREFCs is that TPC should be between the
>> 70% and 90% CL". Does the same guidance apply to completion date? In any
>> case, do we have from the MC completion dates for less than 90% CL; it
>> might be a natural question to ask what CL we are consistent with at the
>> moment.
>> I would not say the supply chain risks for LAr are "wrong". For the
>> recent NSF risk review, we decided (as I believe did other subsystems) to
>> keep unchanged the supply chain risks for items that are not yet
>> completed; ie. we did not revisit the "standard" impacts assumed
>> previously for the various types of things, such as PCB fab, PCB assy,
>> ASICs, ... The same was true for the DOE side, where we did not see a
>> float problem coming from this on the MC for CD/2-3. So I was not
>> expecting such a stark problem to appear on the NSF side.
>> As I mentioned previously, we can (very) soon retire some of these
>> supply chain risks, at which point there is no need to tweak their
>> potential impacts. For some others, it might be time to revisit the
>> "standard" impact assumptions,
>> I think I will have to add a slide to my L2 talk that proactively
>> addresses these issues. It will likely not deflect the questions that
>> this is going to cause, but at least we will be seen to be tackling them
>> head on.
>> John
>> On 2/25/23 12:13 PM, Gustaaf Brooijmans wrote:
>>>
>>> Hi John,
>>>
>>>>
>>>>
>>>> We are using all the "standard" impacts proposed across the project
>>>> for Supply Chain, eg. up to 4 months delay for PCB fab. The LAr issue
>>>> being revealed here, with the implication we could need an extra ~9
>>>> months more than we have before the needed-at-CERN dates, is maybe a
>>>> reflection of the fact these are (by now) too conservative? Do we
>>>> really want to show this at DR?? It seems to me it could become the
>>>> "dominant issue" of the entire review? And how do we reply when asked
>>>> "what happens if the MC is right and you deliver LAr boards 9 months too
>>>> late"??
>>>
>>> Do you think the supply chain risk registers for LAr are wrong? We
>>> recently had an NSF risk workshop… Anyway, we don’t really have a choice
>>> I think in terms of what we show at the DR. It’s too late to change our
>>> approach.
>>>
>>> I put some text in my slides along the lines of “we might need extra
>>> funds to accelerate production,” I’m happy to hear more creative
>>> suggestions. Of course it’s not a secret for anybody that pixels and
>>> strips for both ATLAS and CMS are in much worse shape.
>>>
>>>
>>>>
>>>> Given we have not seen this problem before yesterday, we don't
>>>> currently have anything prepared to address it. (as requested, I do not
>>>> even have the MC results in my L2 talk) By April, I can see quite a few
>>>> improvements, since the ADC preprod will be done and the lpGBT
>>>> production should be done. Also, we should have received the preprod.
>>>> PA/S (from DOE scope) by then. So we could "retire" those. All that
>>>> would help, but who knows whether it would be enough to get us to 90%CL
>>>> float. We could consider changing some of the assumptions. For
>>>> example, based on recent experience, I don't think a potential 4-month
>>>> delay for PCB fab is a serious possibility anymore. I would be
>>>> comfortable reducing it to 2 months max.
>>>
>>> That’s up to you. I think PCB fab is probably less of an issue now that
>>> China has ended zero-covid. Parts remain an issue, but maybe for FEB2
>>> there are few things that can go wrong there.
>>>
>>>>
>>>> So, bottom line, here are some questions:
>>>>
>>>> - for next week, you are going to show these float results in your
>>>> plenary talk? And if so, what are we going to say? Just say this is a
>>>> current snapshot, discuss the points above, and argue it will be
>>>> "better" by April? That still leaves open for discussion whether it
>>>> will be "good enough", and the answer is that today we don't know. This
>>>> seems problematic to me.
>>>>
>>>
>>> I don’t think we have a choice. Please take a look at my slides. I’m
>>> happy to adjust the text.
>>>
>>>
>>>> - Or, given that all these changes will happen by April, do we choose to
>>>> NOT show the MC schedule result next week? Once the DR is over, we
>>>> could work with Chris to see where we expect things to stand at the time
>>>> of the rebaseline review?
>>>
>>> We have to show MC results. Since this is the DR, I don’t think it’s a
>>> huge deal. We just need to think what the recommendation is we’re
>>> fishing for. Is it “revise the LAr risks” or is it “prepare a plan to
>>> accelerate production should this be needed”?
>>>
>>> Best,
>>>
>>> Gustaaf
>>>
>>>
>>>>
>>>> John
>>>>
>>>> On 2/24/23 5:34 PM, Gustaaf Brooijmans wrote:
>>>>> Hi John,
>>>>> Yes, but it turns out this is all due to supply chain. In the working
>>>>> summary sheet you’ll see I made some small annotations. Without supply
>>>>> chain the 438/461 becomes 251/288, so ~90% CL. We didn’t have supply
>>>>> chain risks at FDR, or at the summer 2021 annula review.
>>>>> Best,
>>>>> Gustaaf
>>>>>> On Feb 24, 2023, at 4:48 PM, John Parsons <parsons AT nevis.columbia.edu>
>>>>>> wrote:
>>>>>>
>>>>>>
>>>>>> Hi Gustaaf,
>>>>>>
>>>>>> I am surprised that @ 90%CL LAr seems to need about 200 "extra"
>>>>>> days (almost a year) beyond the float we have. What is driving that?
>>>>>> We have certainly made a lot of progress since FDR, and were not in
>>>>>> such bad shape back then. We also have more base float now than we
>>>>>> did at FDR, and yet we are "under water"?
>>>>>>
>>>>>> John
>>>>>>
>>>>>> On 2/24/23 4:39 PM, Gustaaf Brooijmans wrote:
>>>>>>> Hello all,
>>>>>>> We think we’ve worked the kinks out of all the numbers. In the
>>>>>>> attached you will find a for presentation tab, as well as a working
>>>>>>> tab with a bit more info on floats, and all the detailed info. Let
>>>>>>> us know if you see something weird. The for presentation tab
>>>>>>> calculates % contingency on the cost-to-go, which gives a better idea
>>>>>>> of where we are.
>>>>>>> Best,
>>>>>>> Chris and Gustaaf
>>>>>>> _______________________________________________
>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>>>>>
>>>>>> --
>>>>>> ______________________________________________________________________
>>>>>>
>>>>>> John Parsons
>>>>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>>>>> Columbia University Phone: (914) 591-2820
>>>>>> P.O. Box 137 Fax: (914) 591-8120
>>>>>> Irvington, NY 10533 WWW:
>>>>>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ATTa3UccW5aMhNWSz563so0JzvykUJ9g-gcy_ENT7YU-65fN4bgzc-xWXhaRqBV3_Svat5S2RPG9pRBhIaLAMNoVTRQ0r9ewgePJKW8NmaezycKZf-n95A$
>>>>>>
>>>>>>
>>>>>> ______________________________________________________________________
>>>>>>
>>>>
>>>> --
>>>> ______________________________________________________________________
>>>>
>>>> John Parsons
>>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>>> Columbia University Phone: (914) 591-2820
>>>> P.O. Box 137 Fax: (914) 591-8120
>>>> Irvington, NY 10533 WWW:
>>>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ATTa3UccW5aMhNWSz563so0JzvykUJ9g-gcy_ENT7YU-65fN4bgzc-xWXhaRqBV3_Svat5S2RPG9pRBhIaLAMNoVTRQ0r9ewgePJKW8NmaezycKZf-n95A$
>>>>
>>>>
>>>> ______________________________________________________________________
>>>>
>>>
>>>
>
> --
> ______________________________________________________________________
>
> John Parsons
> Nevis Labs, Email: parsons AT nevis.columbia.edu
> Columbia University Phone: (914) 591-2820
> P.O. Box 137 Fax: (914) 591-8120
> Irvington, NY 10533 WWW:
> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!ATTa3UccW5aMhNWSz563so0JzvykUJ9g-gcy_ENT7YU-65fN4bgzc-xWXhaRqBV3_Svat5S2RPG9pRBhIaLAMNoVTRQ0r9ewgePJKW8NmaezycKZf-n95A$
>
>
> ______________________________________________________________________<Screen
> Shot 2023-02-26 at 1.57.28 PM.png>