usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
[Usatlas-hllhc-l2deputymgmt-nsf-l] I&I cost/effort in the NSF CA
- From: "Evans, Harold G." <hgevans AT indiana.edu>
- To: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Cc: "torrence AT uoregon.edu" <torrence AT uoregon.edu>, "john.hobbs AT stonybrook.edu" <john.hobbs AT stonybrook.edu>
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] I&I cost/effort in the NSF CA
- Date: Thu, 25 May 2023 19:30:31 +0000
Hi all,
Here is the latest version of the NSF Cooperative Agreement effort and cost calculations that I could find. John Hobbs should speak up if this is not the actual version used in the proposal. In any case, any small differences won't be relevant to our purpose
 of setting the scale of I&I that we should be aiming for. That's set by the total I&I budget of $6.4M. 
A few (hopefully) clarifying comments:
1. I&I numbers can  be found at the bottom of the "Roll Up" tab.
2. The assignment of funding to institute was done simply based on the fraction of the MREFC budget assigned to each institute. This can certainly be adjusted in constructing our new plan.
3. The CA budget years start on February 1. This leads to the following date mapping:
| NSF proposal "year" | Actual Dates | Budget Table Heading | 
| 1 | 2/1/22 -1/31/23 | 2023 | 
| 2 | 2/1/23 - 1/31/24 | 2024 | 
| 3 | 2/1/24 - 1/31/25 | 2025 | 
| 4 | 2/1/25 - 1/31/26 | 2026 | 
| 5 | 2/1/26 - 1/31/27 | 2027 | 
Please use these numbers as a "baseline" when you construct your updated I&I effort estimates. Let me know if you have any questions...
Thanks  -  Hal
--
------------------------------------------------------------------------------
 Hal Evans                        hgevans AT indiana.edu
 Tel: (812)856-3828                    Fax: (812)855-5533
 204 Swain Hall West               Indiana University
 727 E. Third St.                Bloomington, IN 47405
------------------------------------------------------------------------------
Attachment:
SBU_operations_totals_merged.xlsx
Description: SBU_operations_totals_merged.xlsx
- 
        [Usatlas-hllhc-l2deputymgmt-nsf-l] I&I cost/effort in the NSF CA,
        Evans, Harold G., 05/25/2023
- 
            
            Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] I&I cost/effort in the NSF CA,
            John Hobbs, 05/25/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: I&I cost/effort in the NSF CA, Evans, Harold G., 05/25/2023
 
 
- 
            
            Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] I&I cost/effort in the NSF CA,
            John Hobbs, 05/25/2023
Archive powered by MHonArc 2.6.24.