Today’s update:
-6.4 and 6.4.2 are missing
-6.4.1: In general it looks good, but the sense "We have currently received
about 20% of the scheduled 50% of the total production for LAr” is a bit
strange. Does it mean we were scheduled to have received 50% and we got 20%?
Anyway, the VR needs to be submitted for me to approve it.
-6.6 is missing (check with Penka on authorization)
-6.6.3: "The positive cost variance stems from design issues with the sMDT
mezz card by MPI, resulting in some planned work not started. “ => delayed
work cannot lead to a cost variance, so I have re-opened this
-6.6.4 looks good now, thanks. I have approved it.
-6.6.5 I have approved
-6.8.4 is missing
Best,
Gustaaf
> On Jun 18, 2024, at 14:59, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
> wrote:
>
>
> Hello all,
>
> A reminder that the May VRs are due soon. Keep in mind that the May
> working schedule is our basis for the July review, so it’s crucial to fully
> understand the variances. This will have to go into your slides.
>
> Many are already posted (thanks!), here are some comments:
>
> -6.4.3 looks good, I have approved it
>
> -6.5.4: I don’t understand this: any pre-rebaselining variance would have
> been zeroed out, and in fact there is no variance at Columbia. I have
> unlocked this.
>
> -6.6.3: the SV report looks fine, but CV is missing, so I have unlocked
> this.
>
> -6.6.4: "The schedule variance of $866k is mostly due to delays in the
> schedule. We are set to enter full production now, so are hit with a
> variance of roughly $720k.” This basically says there is a schedule
> variance because there is a schedule variance. Please say something about
> the actual source. (I guess it’s purchase of comonents…) I have unlocked
> this.
>
> -6.6.5: looks good but you forgot to submit. (BTW, I think you meant
> “remainder” rather than “reminder”)
>
> -6.8 looks good and I have approved.
> -6.8.3: nice to see a $100k positive variance this month. I approved the
> text.
>
> Best,
>
> Gustaaf
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs,
Gustaaf Brooijmans, 06/18/2024
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs,
Gustaaf Brooijmans, 06/19/2024
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs,
Gustaaf Brooijmans, 06/20/2024
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs, Gustaaf Brooijmans, 06/24/2024
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs,
Gustaaf Brooijmans, 06/20/2024
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs,
Gustaaf Brooijmans, 06/19/2024
Archive powered by MHonArc 2.6.24.