  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] May VRs
  • Date: Mon, 24 Jun 2024 11:17:00 +0200


Hello all,

We’re now just missing 6.6 and the revision to 6.6.3.

Thanks,

Gustaaf

> On Jun 20, 2024, at 11:03, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
> wrote:
>
>
> Thursday’s update:
>
> -LAr is complete and fully approved
>
> -We’re missing 6.6 and the revision to 6.6.3
>
> -We’re missing 6.8.4
>
> All the rest was already approved.
>
> Best,
>
> Gustaaf
>
>> On Jun 19, 2024, at 11:23, Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
>> wrote:
>>
>>
>> Today’s update:
>>
>> -6.4 and 6.4.2 are missing
>>
>> -6.4.1: In general it looks good, but the sense "We have currently
>> received about 20% of the scheduled 50% of the total production for LAr”
>> is a bit strange. Does it mean we were scheduled to have received 50% and
>> we got 20%? Anyway, the VR needs to be submitted for me to approve it.
>>
>> -6.6 is missing (check with Penka on authorization)
>>
>> -6.6.3: "The positive cost variance stems from design issues with the sMDT
>> mezz card by MPI, resulting in some planned work not started. “ => delayed
>> work cannot lead to a cost variance, so I have re-opened this
>>
>> -6.6.4 looks good now, thanks. I have approved it.
>>
>> -6.6.5 I have approved
>>
>> -6.8.4 is missing
>>
>> Best,
>>
>> Gustaaf
>>
>>> On Jun 18, 2024, at 14:59, Gustaaf Brooijmans
>>> <gusbroo AT nevis.columbia.edu> wrote:
>>>
>>>
>>> Hello all,
>>>
>>> A reminder that the May VRs are due soon. Keep in mind that the May
>>> working schedule is our basis for the July review, so it’s crucial to
>>> fully understand the variances. This will have to go into your slides.
>>>
>>> Many are already posted (thanks!), here are some comments:
>>>
>>> -6.4.3 looks good, I have approved it
>>>
>>> -6.5.4: I don’t understand this: any pre-rebaselining variance would have
>>> been zeroed out, and in fact there is no variance at Columbia. I have
>>> unlocked this.
>>>
>>> -6.6.3: the SV report looks fine, but CV is missing, so I have unlocked
>>> this.
>>>
>>> -6.6.4: "The schedule variance of $866k is mostly due to delays in the
>>> schedule. We are set to enter full production now, so are hit with a
>>> variance of roughly $720k.” This basically says there is a schedule
>>> variance because there is a schedule variance. Please say something
>>> about the actual source. (I guess it’s purchase of comonents…) I have
>>> unlocked this.
>>>
>>> -6.6.5: looks good but you forgot to submit. (BTW, I think you meant
>>> “remainder” rather than “reminder”)
>>>
>>> -6.8 looks good and I have approved.
>>> -6.8.3: nice to see a $100k positive variance this month. I approved the
>>> text.
>>>
>>> Best,
>>>
>>> Gustaaf
>>> _______________________________________________
>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>
>> _______________________________________________
>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l





Archive powered by MHonArc 2.6.24.

Top of Page