usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings
- Date: Thu, 6 Jun 2019 14:07:17 -0400
Tim/Andy,
We need to schedule the NSF risk scrubbing with the PO,
so I need you to get back to me today with your availability,
as requested below.
John
-------- Forwarded Message --------
Subject: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings
Date: Tue, 4 Jun 2019 14:31:38 -0400
From: John Parsons <parsons AT nevis.columbia.edu>
To: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings
Date: Tue, 4 Jun 2019 14:04:30 -0400
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
Hello all,
Given that we'll need to run the simulation again after the risk scrubbing, we'd like to complete these sessions by June 21 at the latest. We expect these to require ~half a day per system. Tile is going first at 2:30 pm eastern this week:
https://indico.bnl.gov/event/6236/
John, Hong, Tom, Anyes, Elliot and Tae, could you identify a half day each between June 11 and 21 where we can hold these? I will be in Europe starting on the 12th, so if it is possible to do it during the morning US time that would be great.
Thanks,
Gustaaf
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings,
John Parsons, 06/04/2019
-
[Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings,
John Parsons, 06/06/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings, John Parsons, 06/06/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings, John Parsons, 06/07/2019
-
[Usatlas-hllhc-lartl2l3-l] Fwd: Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] Scheduling risk scrubbings,
John Parsons, 06/06/2019
Archive powered by MHonArc 2.6.24.