[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Schedule and estimation type reports
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Schedule and estimation type reports
- Date: Thu, 11 Jul 2019 17:20:08 -0400
Sorry, somehow I overlooked this email so didn't forward it,
but the new cost tables etc. for NSF are available in
docdb; see below. These are the versions to be used for
the upcoming NSF FDR DR.
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Schedule and estimation type reports
Date: Wed, 3 Jul 2019 20:28:05 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: 'usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov' <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
*From:* Novakova, Penka N <penka AT bnl.gov>
*Sent:* Wednesday, July 3, 2019 4:23 PM
*To:* Usatlas-hllhc-l2deputymgmt-nsf-l <usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov>
*Subject:* Schedule and estimation type reports
Schedule and estimation type reports have been posted in the same documents as the cost books.
* 6.4 – LAr – 840
* 6.5 – Tile – 841
* 6.6 – Muon – 842
* 6.8 – Trigger – 843
Please review and let us know if anything needs to be fixed.
Thank you,
penka
*From:* Usatlas-hllhc-l2deputymgmt-nsf-l <usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov <mailto:usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov>> *On Behalf Of *Freedman, Rhoumela
*Sent:* Friday, June 28, 2019 2:11 PM
*To:* 'usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov' <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <mailto:usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>>
*Subject:* [Usatlas-hllhc-l2deputymgmt-nsf-l] BOE Tables, Cost Books and Drilldown Reports
Hi everyone,
The BOE Tables, Cost Books and Drilldown Reports have been posted up on DocDB. Here are the respective DocDB Numbers for each system:
* 6.4 – LAr – 840
* 6.5 – Tile – 841
* 6.6 – Muon – 842
* 6.8 – Trigger – 843
Please let me know if you have any questions.
Thank you,
Rhoumela
Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory, Physics Dept.
Tel: (631) 344-3460
Fax: (631) 344-6179
rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
- [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] FW: Schedule and estimation type reports, John Parsons, 07/11/2019
Archive powered by MHonArc 2.6.24.