Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2
- From: Tim Andeen <timothy.robert.andeen AT cern.ch>
- To: John Parsons <parsons AT nevis.columbia.edu>
- Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2
- Date: Fri, 12 Jul 2019 10:49:32 +0200
Hi John,
Name was: Material for VL+ Quad TX Prototype - 120 VL+ @ $120 Each
Change to: Material for VL+ for FEB2 Prototype
Direct cost was: $17,850
Change to: $24,000
Delta: $6150
You are correct, this did not reflect the new cost sharing for the optics or the ADC. I've attached a corrected version now with the changes highlighted in red.
I also double checked this against what is in the drill down report in docdb840. The cost sharing is in the report. However, I found three new changes. They are small, but I know this will still require a BCP, not sure when that should happen. Two are name changes I asked for didn't get propagated in in the last update. And one change to the cost of the VL+ chips for the prototype FEB2 that I think I missed (delta of +$6150). The relevant parts lines are:
6.04.01.03.04 FE Electronics-SMU VL+
FEE30495M |
Change to: Material for VL+ for FEB2 Prototype
Direct cost was: $17,850
Change to: $24,000
Delta: $6150
FEE30540M40
Name was: PMT: VL+OTX Production - 10,400 Quad @120 Each, 3,500 Single @30 Each 67% Cost Sharing
Change to: PMT: VL+OTX Production
Best, Tim
Name was: PMT: VL+OTX Production - 10,400 Quad @120 Each, 3,500 Single @30 Each 67% Cost Sharing
Change to: PMT: VL+OTX Production
Best, Tim
On Thu, Jul 11, 2019 at 11:51 PM John Parsons <parsons AT nevis.columbia.edu> wrote:
Hi Tim,
Does it properly reflect the update % sharing
from the recent adjustments? I think the optics needs
to be updated, right?
John
On 7/8/19 5:12 AM, Tim Andeen wrote:
> Hi John,
>
> What is in there now is good. I think I iterated on this Gustaaf a
> week(?) ago, and it's still OK.
>
> Best, Tim
>
> On Fri, Jul 5, 2019 at 6:39 PM John Parsons <parsons AT nevis.columbia.edu
> <mailto:parsons AT nevis.columbia.edu>> wrote:
>
>
> Tim/Andy,
>
> Something that needs to be filled out for ICE.
> Please get it back to me by COB on Wed. July 10 so I have
> time to put it together.
> Regards,
> John
>
> -------- Forwarded Message --------
> Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2
> Date: Fri, 5 Jul 2019 10:36:19 -0400
> From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
> <mailto:gusbroo AT nevis.columbia.edu>>
> To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
> <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>>
>
>
> Hello all,
>
> So-called "phase-1" of the ICE (Independent Cost Estimate) is now
> coming
> to a close. After some struggles, we agreed that the BOEs were too
> complex and that the starting point for the ICE would be a master
> spreadsheet listing the documents used to
> a) explain what the deliverable is, and
> b) obtain quotes
>
> Attached is the master sheet, which we need to send to NSF fully filled
> out on July 15. Therefore, we need you to return it by *COB Thursday
> July 11*.
>
> The sheet is largely self-explanatory, but the Tile Main Board can
> serve
> as an example. What you need to do is
>
> 1) Check that I got all the relevant lines, i.e. all the lines that
> include material costs relevant to deliverable construction
>
> 2) Fill out columns H to Q. In many cases I put in educated guesses,
> these may be wrong. A few specific comments:
> *J: this is an index to indicate if multiple payments correspond
> to a
> single quote (eg Tile Main Board assembly batches)
> *M: make sure you have these documents: in a few more weeks we'll
> need to provide them so they can get quotes. Looking through the
> packages put together for our initial attempt, I did not always see
> gerber files where I expected them)
> *O: to my knowledge, only ASICs made under the CERN frame contract
> only have one possible vendor, but that may be incorrect.
> *P: indicate here if you applied any kind of scaling, eg because
> you
> used a different board's gerber to get a quote
> *Q is about documentation that explains the deliverable, but is not
> used in obtaining quotes.
>
> Any questions, let us know.
>
> Best,
>
> Gustaaf
>
> _______________________________________________
> Usatlas-hllhc-lartl2l3-l mailing list
> Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
>
>
>
> --
> ---------------
> Tim Andeen
> Assistant Professor, Department of Physics
> College of Natural Sciences
> The University of Texas at Austin
> Austin, TX 78712-1192
> web: tandeen.web.cern.ch <http://tandeen.web.cern.ch>
> office (TX): PMA 10.208
> office (CERN): 304/1-024
> ph (TX): +1 512 475-9575
> ph (CERN): +41 (0)22 76 758 14
> email: tandeen AT utexas.edu <mailto:tandeen AT utexas.edu>
> ---------------
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: http://www.nevis.columbia.edu/~parsons/
______________________________________________________________________
---------------
Tim Andeen
Assistant Professor, Department of Physics
College of Natural Sciences
The University of Texas at Austin
Austin, TX 78712-1192
web: tandeen.web.cern.ch
office (TX): PMA 10.208
office (CERN): 304/1-024
ph (TX): +1 512 475-9575
ph (CERN): +41 (0)22 76 758 14
email: tandeen AT utexas.edu
---------------
Tim Andeen
Assistant Professor, Department of Physics
College of Natural Sciences
The University of Texas at Austin
Austin, TX 78712-1192
web: tandeen.web.cern.ch
office (TX): PMA 10.208
office (CERN): 304/1-024
ph (TX): +1 512 475-9575
ph (CERN): +41 (0)22 76 758 14
email: tandeen AT utexas.edu
---------------
Attachment:
ICE-large-procurements_check2.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2,
John Parsons, 07/05/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2,
Tim Andeen, 07/08/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2,
John Parsons, 07/11/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2, Tim Andeen, 07/12/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2,
John Parsons, 07/11/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF ICE sheet, phase-2,
Tim Andeen, 07/08/2019
Archive powered by MHonArc 2.6.24.