usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-management-l] LAr replies to COVID delays

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: John Parsons <parsons AT nevis.columbia.edu>, "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] [Usatlas-hllhc-management-l] LAr replies to COVID delays
  • Date: Mon, 6 Apr 2020 11:24:53 +0200


Hi John,

Thanks. A couple of comments:
-we already had the BE firmware specs review.
-I don't think you should write "This is roughly estimated based on past experience (though we obviously don’t have directly comparable previous experience)".
-You write "This work cannot be done remotely... An estimate of the quantitative impact is a 3-month delay and increased labor costs of $30k." We'll need to be careful with such statements, as they indicate standing army. We don't have a clear statement from NSF yet about standing army. We'll try to get that asap.

Best,

Gustaaf


On 4/5/20 1:12 AM, John Parsons wrote:

Hi all,

    I attach the LAr replies to various COVID scenarios, as requested.
    Regards,
        John