usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2020 Status Sheets
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2020 Status Sheets
- Date: Sun, 24 May 2020 13:13:27 -0400
Hi all,
It is time again for the monthly status sheet and list of technical bullets. Please complete both asap, and not later than COB this Tuesday, and keep in mind (particularly for the NSF) the discussions we had on Friday.
I hope you are all enjoying the Memorial Day weekend!
Regards,
John
P.S. There was some good news out of NY (see https://urldefense.com/v3/__https://abc7ny.com/westchester-county-reopening-rockland-nassau-suffolk/6206691/__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLJrLVzCd$ ), suggesting that Westchester and Long Island could start gradual re-opening this coming week (though it is still not clear when NYC will reach this milestone).
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] May 2020 Status Sheets
Date: Fri, 22 May 2020 18:55:02 +0000
From: Freedman, Rhoumela <rfreedman AT bnl.gov>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov <usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
Dear All,
*If you need help pleaseDO NOT reply to the mailing list*
**** The */Pre-Status Reports/*/*for May 2020*/ have been uploaded in *DocDB 976*. These are the Gantt Charts for each subsystem. Please make sure to look over the chart while doing your Status Updates. ****
The status sheets for the month of May are now available in google docs:
·6.01 - Pixels - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1pJVgvOXLCJav-l7Wkj4xZhNXPlw51TTEF5owBb9u0P4/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLGj0VE4j$
·6.02 - Strips - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1Xnh9uFqzhc-Yf2OksxoDjqTT35ulYCXp3DxkA-zL4gQ/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLNdiqQ5R$
·6.03 - GM -https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1jxK1ppRAmISNLciGsbUDl7M72eAM7C_KmwMf4Q3k3VU/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLB55q-7I$
·6.04 - LAr - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1hytJtDiW09I1A3tuDijRfWbxl1Xs8GgK0qewxcrDneg/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLGTTaIDd$
·6.05 - Tiles - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1EsyiIOambsgULDb4enW0NGaD4r5G5qUJ263Bpqg0h7E/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLIK0Thq5$
·6.06 - Muons - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1P7tkT1fdluB8jqtWzYw2poVbESEM7kC5g7c-aQDyAd4/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLIaRlKFY$ ,
·6.07 - DAQ - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1-X0MSo5E4CFCZzZrYDYyg8SxB6vX1KlmcqOuGwfKXDY/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLBuuQR2d$
·6.08 - Trigger - https://urldefense.com/v3/__https://docs.google.com/spreadsheets/d/1OAVSlb_jgMFV7XO2kgz6KPWfGXbJIfpPc6PkJJaOtVA/edit?usp=sharing__;!!P4SdNyxKAPE!TN5kyfKVsUN3OLWUWyeNTd_1mSkreX61UGcybu-JR7-W3eulwdvBzUVIJGhfPTvhxeKsmToqeEVeLHLR04Iw$
Please remember to update the status online – DO NOT download the files.
The reports are at L2. The reports contain activities for October 2019-September 2020. You can filter for your CAM name in column D.
**** PLEASE NOTE THE FOLLOWING INSTRUCTIONS IN FILLING OUT YOUR STATUS SHEETS: ****
1. In this months’ status sheets we have added new column for resources
(column O) and Planned/Remaining Units (hours for labor and direct
cost for material/travel) in columns P and Q. The remaining units
are calculated based on the original duration of the activity and
percent complete. We have added *column R* in which we are asking
you to update the **Units to Complete** based on your experience and
expectations. This is only in case you expect to spend more or less
labor for the specific activity or the cost for material/travel is
different than originally estimated. Column S show Total Cost per
resource from P6. Columns T (Remaining Cost based on the remaining
units from P6), U (Updated Remaining Cost, also called ETC or
Estimate-to-Complete), V (EAC or Estimate at Complete, calculated
based on updated units) and W (Delta EAC minus baseline cost) are
formula fields that provide calculations on how the cost changes
when the Remaining Units are adjusted.
2. Please provide status in columns K, L, M, N, and R. Make sure that
for all activities in progress you provide **Expected Finish**
(column N). This is important for us to re-calculate the float and
the critical path.
3. Make sure that you enter the actual start date for all started
activities and finish date for all activities that are 100%
completed. All *_NEW_* actual start and finish dates *MUST BE*
within current reporting period.
4. Do *NOT *change the actual start/finish dates if they are already in
the spreadsheet – EVMS does not allow changing the past. If the
actual start date was entered incorrectly in the previous month just
leave it as it is.
5. Do *NOT* enter dates after May 31, 2020 in actual start/finish
dates (columns L and M) , this creates errors in P6.
6. Do *NOT* decrease percent complete in column K.
7. Do *NOT* write any notes in the spreadsheet, if you want to add a
comment use column X.
Please complete the May status update by Thursday, May 28.
We expect that the L2 managers and deputies will notify us (Penka, Carrie, Jenn, Rhoumela) as soon as the status for their system is complete.
Let us know if you have any questions or comments/suggestions to make the process smoother and more user-friendly.
Thank you!
Rhoumela Freedman, Administrator
U.S. ATLAS HL-LHC Upgrade Project
Brookhaven National Laboratory, Physics Dept.
Tel: (631) 344-3460
Fax: (631) 344-6179
rfreedman AT bnl.gov <mailto:rfreedman AT bnl.gov>
_______________________________________________
Usatlas-hllhc-l2l3ics-l mailing list
Usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2l3ics-l
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2020 Status Sheets,
John Parsons, 05/24/2020
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] May 2020 Status Sheets, Ma, Hong, 05/26/2020
Archive powered by MHonArc 2.6.24.