  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2deputymgmt-doe-l] NSF Risk Review on April 12
  • Date: Fri, 1 Apr 2022 12:20:39 -0400


FYI

-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2deputymgmt-doe-l] NSF Risk Review on April 12
Date: Mon, 28 Mar 2022 14:39:05 +0000
From: Meyer, Christopher John <cjmey AT iu.edu>
To: Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov>, usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>



Dear L2s and Deputy L2s,

Apologies, I accidentally sent this to the DOE list instead of NSF and DOE. I've copied the message below again; apologies if you're getting this twice!

As discussed at the March 15^th CCB meeting, we'd like to have a quarterly *NSF risk review*, which we propose to hold during the CCB meeting time slot on*Tuesday, April 12^th *. As these reviews are becoming more streamlined, we think we can cover all systems in one meeting (10 min per subsystem).  The agenda page is here:

https://indico.bnl.gov/event/15288/ <https://indico.bnl.gov/event/15288/>

I've uploaded the Risk Register Pointer slides from March 15^th  in case it's helpful to reference them when putting together your slides. As usual, please*prepare a few slides of your own*covering:

* Changes in risks since the last risk review
* Updated tasks affected (to make sure it is something in the future)
as well as clear descriptions of what to do in case of multiple
tasks affected (rare)
* Updated comments to clearly describe cost/duration uncertainties
* Potential changes to risks in the next 3 months, e.g.
*
o changes to probability/impact of existing risks
o existing risks that could be realized or that need to be watched
carefully
o introduction of new risks, or even just speaking to the things
that are worrying you these days
o risks that might be retired
* This is also an opportunity for general housekeeping of the RR, e.g.
updating anticipated risk retirement dates

The risk register in docDB has been updated to v68:

https://atlas-hllhc.docdb.bnl.gov/0001/000196/082/Risk-Register_v68.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/082/Risk-Register_v68.xlsx>

For the *DOE folks*, we will be in touch about your risk review very soon.

Any issues, please let us know.

    - Your friendly PO_______________________________________________
Usatlas-hllhc-l2deputymgmt-doe-l mailing list
Usatlas-hllhc-l2deputymgmt-doe-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-doe-l



Archive powered by MHonArc 2.6.24.

Top of Page