  • From: "Ma, Hong" <hma AT bnl.gov>
  • To: Tim Andeen <tandeen AT utexas.edu>, "Parsons, John" <parsons AT nevis.columbia.edu>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] weekly mtg and other issues
  • Date: Tue, 3 May 2022 01:28:44 +0000

Hi Tim,

                I don’t know what happened, but I had the right BOE text on the slide, but the wrong text in the BOE file.    

                I have corrected them now.   Both the slides and BOE are _V3 on the indico page.

 

                For the package from JCET, I now say it is the contract, instead of quote.

                I updated the date.

                Unfortunately, the translation from the quote to the US cost is not straightforward, because of core and non-core cost.  It is fully documented in the traceability table.

 

                The numbers in BOE cost table are direct cost, while the cost from scrubbing report on slide 2 is the actual cost.  I think that is why they are different.

 

                Thanks a lot for spotting the error.

 

                Hong.

 

 

From: Tim Andeen <tandeen AT utexas.edu>
Date: Monday, May 2, 2022 at 3:21 PM
To: Parsons, John <parsons AT nevis.columbia.edu>, Ma, Hong <hma AT bnl.gov>
Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] weekly mtg and other issues

Hi Hong, 

 

I made some comments directly on the word doc and ppt slides and uploaded them to the indico page: 

 

My main concern is that there seems to be an inconsistency in the BOE text and the example drill down (at least in the version that you uploaded). Related ,the packaging costs in the BOE don’t match the tables or slides, and I couldn’t see how you got $29k for preproduction and $86k for production. Also the cost estimate table in the BOE material costs don’t match your slide 2 table. Are they supposed to? 

 

Best, Tim

 

__________________________________________________

Tim ANDEEN | Associate Professor | Department of Physics     
College of Natural Sciences | The University of Texas at Austin
tandeen AT utexas.edu | tandeen.web.cern.ch
office (TX) PMA 10.208 | (CERN)  304/1-024
ph (TX):  +1 512 475-9575 | (CERN): +41 (0)22 76 758 14

__________________________________________________


On May 2, 2022 at 1:49:14 PM, Andy Haas <andy.haas AT nyu.edu> wrote:

Here are my comments on Hao's slides and BOE.

Slide 2: This is the total cost _after_ BCP 069?
Why BNL_P_3_AP2 BNL Professional 3 so high in FY24?
What is BCP 075 for?

Slide 3: What is the effect on this WBS from the COVID BCP?
The BE crate setup will be built at CERN, but by who? BNL still? The
BOE still says "The backend test stand will be built to perform the
integration test of the BE electronics...".
Has the BOE just not been updated??
I still don't know what BCP 075 will do.

Slide 5: The first table is too fuzzy to read.
That fuzzy table seems to include 17k for "software", but isn't that
already in the second table? What is the software?

For the BOE:
I don't understand why it talks about "test board manufacturing
costs". The slides indicate that we're just buying dev boards. Are we
building any boards in this WBS??
Since the majority of the cost of this WBS is labor, and it's based on
phase I (and earlier) experience, could we not have an attachment
detailing the phase I labor? In general, it's not very clear exactly
what each person is working on and when for this WBS.


On Wed, Apr 27, 2022 at 10:46 PM John Parsons
<parsons AT nevis.columbia.edu> wrote:

 

 

Hi all,

 

         We will meet Friday at our usual time.  The indico page is at

https://urldefense.proofpoint.com/v2/url?u=https-3A__indico.bnl.gov_event_15546_&d=DwICAg&c=slrrB7dE8n7gBJbeO0g-IQ&r=y4qQBOsjsdgJNx-_8SvpS9786vHE4GOddPXp1ozJgWc&m=KYta6_jQMkuN6xO_qteMf60cetz0s9eRiWRDMinw9G7jS8gX-Qfwc5nmfe1tMV4S&s=rfZFGpknDud1G2UHzzVvYgCd4ZZlmW66i3DjfVPF5k8&e= .  In addition to the usual

roundtable, we will discuss preparations for the DOE RLS scrubbing that

will happen next Wed. (see https://urldefense.proofpoint.com/v2/url?u=https-3A__indico.bnl.gov_event_15406_&d=DwICAg&c=slrrB7dE8n7gBJbeO0g-IQ&r=y4qQBOsjsdgJNx-_8SvpS9786vHE4GOddPXp1ozJgWc&m=KYta6_jQMkuN6xO_qteMf60cetz0s9eRiWRDMinw9G7jS8gX-Qfwc5nmfe1tMV4S&s=8ExQigeuYbHqw5bcu5I5m24XJ2AX6W8MCu07aY4C_eg&e= ).

        Before Friday's meeting, Hong and Hao should upload to Friday's Indico

their relevant documents for the scrubbing.  We will look at them

briefly together on Friday. Then, to help with the DOE scrubbing

preparations, I would like to ask Tim to read over Hong's PA/S

documents, and Andy to read over Hao's System Integration documents, and

to provide feedback latest by noon on Tues. May 3.  I will also go over

both sets of documents.  That should give Hong and Hao some time to

incorporate any changes before the scrubbing with the PO on Wed. May 4.

 

        Another issue: during our weekly meeting on Apr. 8, we went over any RR

changes to be made as part of the quarterly RR review. I need now to

collect all the final changes and propagate them to the PO. Please make

sure the RR version you uploaded to the Apr. 8 Indico reflects all the

changes to be made to your L3, updated as necessary following the

discussions we had.

 

        Regards,

                John

--

______________________________________________________________________

 

John Parsons

Nevis Labs,             Email: parsons AT nevis.columbia.edu

  Columbia University   Phone: (914) 591-2820

P.O. Box 137            Fax: (914) 591-8120

Irvington, NY 10533     WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!EDJ0xTiX8R3JTLcscZdIjkPDQoAUKmtQqAblx00Kbgwus5_vgAInDVBAH7aAX0tRl9a7LfPFvnpL16LC3ptlN7E9rNL7nVfZyDgqHJCsV_wQNg$

 

______________________________________________________________________

_______________________________________________

Usatlas-hllhc-lartl2l3-l mailing list

Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

https://urldefense.proofpoint.com/v2/url?u=https-3A__lists.bnl.gov_mailman_listinfo_usatlas-2Dhllhc-2Dlartl2l3-2Dl&d=DwICAg&c=slrrB7dE8n7gBJbeO0g-IQ&r=y4qQBOsjsdgJNx-_8SvpS9786vHE4GOddPXp1ozJgWc&m=KYta6_jQMkuN6xO_qteMf60cetz0s9eRiWRDMinw9G7jS8gX-Qfwc5nmfe1tMV4S&s=Th8de8rofJvs5u5feRTfAj0Ebzy_c-Gxsj6nWlgrCeg&e=

_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l




Archive powered by MHonArc 2.6.24.

Top of Page