usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
[[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24
- Date: Sat, 24 Jan 2026 14:22:02 -0500
!-------------------------------------------------------------------|
This Message Is From an External Sender
This message came from outside your organization.
|-------------------------------------------------------------------!
FYI. The NSF L3s should review their RR entries. I suggest we use our weekly meeting slot on Feb. 13 to review this and discuss any updates that are needed.
(A DOE RR review will take place later in the spring, before it is time to freeze everything to be able to run the MC before the DOE reveiw in May.)
John
-------- Forwarded Message --------
Subject: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24
Date: Sat, 24 Jan 2026 16:25:07 +0000
From: Reinhard Schwienhorst (via usatlas-hllhc-l2deputymgmt-nsf-l Mailing List) <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
Reply-To: Reinhard Schwienhorst <reinhard.schwienhorst AT cern.ch>
To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
CC: usatlas-hllhc-management-l AT lists.bnl.gov <usatlas-hllhc-management-l AT lists.bnl.gov>
Dear NSF L2s and Deputy L2s, We would like to schedule the next NSF risk workshop for Tuesday, February 24 during the CCB meeting. In preparation, please prepare slides that focus on: - Risks that can now be retired. - New risks that might have
ZjQcmQRYFpfptBannerStart
This Message Is From an External Sender
This message came from outside your organization.
ZjQcmQRYFpfptBannerEnd
Dear NSF L2s and Deputy L2s,
We would like to schedule the next NSF risk workshop for Tuesday, February 24 during the CCB meeting.
In preparation, please prepare slides that focus on:
- Risks that can now be retired.
- New risks that might have come up over the past 6 months, or issues that are worrying you these days.
- Large changes in probability or cost/duration uncertainty.
- Updating the task affected so that all tasks associated with risks are in the future.
The current risk register in docDB (#196) is v98, and the supply chain risk register is v16:
https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_v98.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_v98.xlsx >
https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_Supply-Chain_v22.xlsx <https://atlas-hllhc.docdb.bnl.gov/0001/000196/119/Risk-Register_Supply-Chain_v22.xlsx >
Please look over both for this review. In addition to your slides, please also prepare updated versions of these registers with updated cells highlighted.
Any issues, please let me know.
Reinhard, on behalf of your friendly PO
-
[[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24,
John Parsons, 01/24/2026
- Re: [[Usatlas-hllhc-lartl2l3-l] ] Fwd: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] NSF risk worhshop Feb 24, John Parsons, 01/27/2026
Archive powered by MHonArc 2.6.24.