Hi All,
Since I have not received any information about expected space requirements at BNL I did it myself
based on my limited knowledge and assumptons.
Below you see what I quoted that each of the PID detectors might need.

dRICH    
space size: ~360 ft2 high celing 18ft larger doors    
space requirements: Clean room needed for full assembly with mirrors in particular. high ceiling is needed due to size of full detector (~4m diameter) access with lifting gantry capable of 2.5 metric tons max. (detector wight expected to be 2 metric tons.) AC power and internet connectivity.    
time line: 12 month prior to installation in the Hall    
purpose: assembly detector and testing for installation in the HALL

hpDIRC    
space size: ~360 ft2 large doors modules are 12 feet long    
space requirements: Normal lab space with power outlets and ethernet connectivity, Nitrogen gas supply (at atmospheric pressure)    
time line: 9-12 month prior to installation in the Hall    
purpose: testing and preparation for installation in the HALL

pfRICH    
space size: ~300 ft2    
space requirements: Normal lab space with power outlets and ethernet connectivity, Nitrogen gas supply (at atmospheric pressure)    
time line: 6 month prior to installation in the Hall    
purpose: testing and preparation for installation in the HALL


cheers,
Beni