Skip to Content.
Sympa Menu

sphenix-calibration-l - Re: [Sphenix-calibration-l] Input for Collaboration Meeting

sphenix-calibration-l AT lists.bnl.gov

Subject: Sphenix-calibration-l mailing list

List archive

Chronological Thread  
  • From: "Benjamin, Douglas" <dbenjamin AT bnl.gov>
  • To: Ross Corliss <rcorliss AT mit.edu>, Hugo Pereira Da Costa <hugo.pereira-da-costa AT cea.fr>
  • Cc: sphenix calibrations <sphenix-calibration-l AT lists.bnl.gov>
  • Subject: Re: [Sphenix-calibration-l] Input for Collaboration Meeting
  • Date: Mon, 7 Jun 2021 19:42:04 +0000

Hello,

Would it be possible for the 'rev 3' of the flow chart include the merge
steps also listed. If all of the steps are listed in the flow chart then it
more straight forward to understand the intermediate data products, their
sizes, how often they are aggregated. I would like to start to assemble the
processing DAG (at least on paper). The flow chart will be the input to the
DAG, there will be some steps that will need to be run in parallel to produce
enough output for the aggregation steps. I know I might be stating the
obvious but I would like to write it down. If there are a lot of small files
produced by many processes across many nodes, then we need a storage device
that can handle the load. Such things are not cheap.

Regards,

Doug Benjamin


-----Original Message-----
From: sPHENIX-calibration-l <sphenix-calibration-l-bounces AT lists.bnl.gov> on
behalf of Ross Corliss via sPHENIX-calibration-l
<sphenix-calibration-l AT lists.bnl.gov>
Reply-To: Ross Corliss <rcorliss AT mit.edu>
Date: Monday, June 7, 2021 at 2:14 PM
To: Hugo Pereira Da Costa <hugo.pereira-da-costa AT cea.fr>
Cc: sphenix calibrations <sphenix-calibration-l AT lists.bnl.gov>
Subject: Re: [Sphenix-calibration-l] Input for Collaboration Meeting

HI Hugo et al.,

I think the details of how the distortions are derived and combined
(hence the flow chart -- probably a
'rev 3', with the 'validate' step fleshed out) would be good to show,
along with the status of the components. This matches a lot of Hugo's
comments.
Some of the details of the central membrane distortion monitoring (which
we will discuss tomorrow, and hopefully have a pull request before the collab
meeting) have also progressed since last time.

I would be glad to assemble the slides and present the status.

-Ross
> On Jun 7, 2021, at 12:14 PM, Hugo Pereira Da Costa via
sPHENIX-calibration-l <sphenix-calibration-l AT lists.bnl.gov> wrote:
>
> Hello Christof, (repeating here what we discussed semi-privately)
>
> On the track-based space charge distortion reconstruction, there really
have not been much new things since last collaboration meeting, mainly
because things where in a reasonable state by then already.
>
> Obviously, there have been developments on making the TPOT happening
for real (something which is critical to track-based SC corrections), but I
expect this to be covered in a separate talk in the detector section
>
> To me, the newest thing that should really be presented at the
collaboration meeting is the effort, led by Ross, to put all the bits and
pieces we have on the TPC SC distortion correction in a comprehensive flow
chart, organized in a first-pass and second-pass reconstruction.
>
> We should then emphasize which parts of this flowchart are already
there (committed, ready to use), which are 'almost there', and which still
need some significant work. I'll let Ross comment on this (and hopefully
volunteer to present this).
>
> On that topic, one of the missing parts of the flow-chart, namely the
ability for the first-pass reconstruction to store the per-job space-charge
correction matrices in independent, tiny files, together with a separate
process to aggregate, invert these matrices and produce a full map, has been
pushed to our repositories last week. So we are one step closer to having
this flow chart turned into a real thing.
>
> That is all the input I have.
>
> Best,
>
> Hugo
>
>
>
> On 6/4/2021 8:58 AM, Christof Roland via sPHENIX-calibration-l wrote:
>> Thanks to Klaus for pointing this out, obviously the mail should
>> have started with "DeaR Calibration TaskFocre Members"
>>
>> I sincerely apologize!
>>
>> This will go onto my list of the more memorable typos or autocorrect
failures.
>>
>> Cheers
>>
>> Christof
>>
>>
>>> On 4. Jun 2021, at 16:40, Christof Roland via sPHENIX-calibration-l
<sphenix-calibration-l AT lists.bnl.gov> wrote:
>>>
>>> Dead Calibration TaskForce Members,
>>>
>>> we are supposed to provide feedback to Dave & Gunther so they
>>> can set up the program for the upcoming collaboration meeting.
>>>
>>> Could you please provide us with a few line response on the
>>> topics you would want to highlight at the collaboration meeting?
>>>
>>> Please also let us know if you would prefer the usual layout
>>> if a separate report by each subcommittee or if we should
>>> change for this particular meeting to a shorter executive style
>>> report to keep the meeting time short and leaving more time for
>>> discussion, as Gunther and Dave suggested last General Meeting
>>>
>>> Cheers
>>>
>>> Takao & Christof
>>> _______________________________________________
>>> sPHENIX-calibration-l mailing list
>>> sPHENIX-calibration-l AT lists.bnl.gov
>>> https://lists.bnl.gov/mailman/listinfo/sphenix-calibration-l
>> _______________________________________________
>> sPHENIX-calibration-l mailing list
>> sPHENIX-calibration-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/sphenix-calibration-l
> _______________________________________________
> sPHENIX-calibration-l mailing list
> sPHENIX-calibration-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/sphenix-calibration-l

_______________________________________________
sPHENIX-calibration-l mailing list
sPHENIX-calibration-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-calibration-l




Archive powered by MHonArc 2.6.24.

Top of Page