ODH Alarm Testing in Bldg 912 in the area where the sPHENIX Magnet is tomorrow morning.

There should be no work in the area during testing. If you are in the area, even though it is a test, all alarms must be obeyed.

 

From: McIntyre, Gary T
Sent: Wednesday, April 15, 2015 3:01 PM
To: Carroll, Daniel; Than, Yatming (Roberto); Wang, Erdong; Seberg, Scott; Phillips, David B; Kobasiuk, Frederick D; Waide, Cornelius E; Korol, Alex J; Gill, Stephen M; Weiss, Dan
Cc: Belomestnykh, Sergey; Conte, Richard; Reich, Jonathan; Kayran, Dmitry; Xu, Wencan; Sheehy, Brian; Seda, Thomas; Kellermann, Robert; Pendzick, Alexander F; Pontieri, Stephen P; Donaldson, Dennis; Feng, Pei Kuan
Subject: 912 ODH testing

 

Dear Colleagues,

Please see the message below, to me from Wencan Xu, regarding the ODH alarm testing in Building 912.

The testing will start tomorrow morning, Thursday, April 16, instead of the afternoon.

 

To repeat: the ODH Alarm testing will start tomorrow AM for 4-6 hours.

Take care,

Mac

 

 

 

 

Gary,

 

  I just talked with Jonathan and informed him that he can do the test tomorrow morning. And he promise it will be doen by 12:00.

 

Regards,

Wencan

 

 

 

From: McIntyre, Gary T
Sent: Wednesday, April 08, 2015 9:27 AM
To: Carroll, Daniel; Than, Yatming (Roberto); Wang, Erdong; Seberg, Scott; Phillips, David B; Kobasiuk, Frederick D; Waide, Cornelius E; Korol, Alex J; Gill, Stephen M; Weiss, Dan
Cc: Belomestnykh, Sergey; Conte, Richard; Reich, Jonathan; Kayran, Dmitry; Xu, Wencan; Sheehy, Brian; Seda, Thomas; Kellermann, Robert; Pendzick, Alexander F; Pontieri, Stephen P
Subject: RE: 912 ODH testing

 

Dear 912 Residents & Users,

The Access Controls certification of the 912-ODH system will be performed on Thursday, April 16, 2015 between noon and 5:00pm. See Dan Carroll’s note below.

No personnel are to be in the 912 area while this testing is done.  If you have an issue and cannot suspend work in 912 in BLG 912 for the 5-6 hours required, please contact me and Dan ASAP. Thank you.

Mac

 

From: Carroll, Daniel
Sent: Tuesday, April 07, 2015 8:39 AM
To: Than, Yatming (Roberto)
Cc: McIntyre, Gary T; Belomestnykh, Sergey; Conte, Richard; Reich, Jonathan; Kayran, Dmitry; Xu, Wencan; Sheehy, Brian; Seda, Thomas; Kellermann, Robert
Subject: 912 ODH testing

 

Gentlemen,

 

It is time again for Access Controls certification of the 912-ODH system.

http://www.c-ad.bnl.gov/esshq/snd/opm/Ch04/04-120-280-h.PDF

 

During this test, the nitrogen valve will close numerous times, ODH strobes and alarms in Bldg 912 EEBA and inside the ERL blockhouse and Laser Room will also be activated. It would be advantageous for all involved if no personnel are in the 912 area while this testing is done.

 

Please advise a date and time when we can perform the test. Anticipated time to complete is approximately four to six hours.

 

Dan Carroll

Brookhaven National Laboratory

Collider-Accelerator Dep’t

Access Controls Group        

Upton, NY 11973

631 344-4230

dcarroll AT bnl.gov

 