Minutes shift change 2023-04-14

General:
—————
- shield wall is in
- EMCal North preamp cooling enabled

evening:  Oliver
- MVTX chiller alarm
- Cameron instructed to turn off chiller

night:  Ejiro
- incident free

day:  Virginia
- exit sign smoking, disconnected

MBD (Mickey)
- LOTOed out of HV rack
- lock cut
- electrician still need to work -> tomorrow
- will check out detector -> Sunday

HCal (Virginia)
- started taking cosmics
- ironing out issues in procedure
- should hand over to shifters in an hour

EMCal (Sean)
- still working on mapping out detector
- tested interlocks for cooling water for preamps
  - one bad flow switch that needs to be changed
  - will leave 3/4 of North on
  - shift crew should monitor EMCal LV, temperature, flow

TPOT
- no report

TPC (Takao)
- LV was off, not much happened
- Jin has been checking connection of fibers to rack electronics properly connected except for one, good progress

INTT (Rachid)
- all cooling
- working on commissioning on North

MVTX (Cameron)
- all three cooling lines now working
- when setting up for system test found that fiber connections were wrong
- working on fixing that

sEPD (Rosi)
- both N and S frames in
- part of optical fibers there, soon to be mounted

DAQ (Martin)
- seems to be working ok
- couple little hick ups
  - first event wrong
  - ghost ADC board
- slow control machine set up in rack room for direct control in addition to opc
- can read out multiple DCMs from single controller

Magnet (Kin)
- still problem with hipot test

Gas/cooling water (Rob)
- ECW flow rebalanced, bypasses off
- EMCal preamp cooling North on (3/4) (see above)

Plan of the day
- Shift crew monitor EMCal preamp cooling

---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------





  • [Sphenix-run-l] Minutes shift change 2023-04-14, Stefan Bathe, 04/14/2023

Archive powered by MHonArc 2.6.24.

Top of Page