News from today’s 9 o’clock meeting (5/13)
- one turn of blue beam achieved last night, but not all goals were achieved, so we are two days behind now
- cryo issue at 56 MHz cavity, needs access to fix, two days of work needed
  - small amounts of beam still possible (56 bunches with 1*10^9) during that time whenever cryo access is interrupted
- PS wants rings to be closed so they can work on ramps ==> conflict with cryo work, need to coordinate
- pulsed power
- malfunction in blue line no. 1:  probably air; investigating

STAR:  TPC problem
- multiple issues with read-out board
- probably from cooling water leak
- need to open pole tip to fix
- about 14 h
- preparing 
- plan to do that on Tuesday

sPHENIX:  TPC problem fixed
- ready for collisions
- waiting for approval for gas and magnet

Conclusion for sPHENIX:
- beginning of commissioning with beam now expected for Friday morning +/- 2 days
- expect long period of RA on Tuesday (b/c of STAR work)

---------------------------------------------------------------------------------
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist

Baruch:                                     BNL:
17 Lexington Ave                      Bldg. 510
office 940                                  office 2-229
phone 646-660-6272                phone 631-344-8490
----------------------------------------------------------------------------------





  • [Sphenix-run-l] News from today’s 9 o’clock meeting (5/13), Stefan Bathe, 05/13/2023

Archive powered by MHonArc 2.6.24.

Top of Page