Hi Gerard, Steve,
Regarding the number of test cables, I propose that we make 10 of them, so
that BNL/UIC/IU/NCKU/SDU can each have 1-2 of them for different purposes.
We can make the length of the cables, according to Rahul’s estimation, 8
feet.
Zhenyu
> On Feb 19, 2019, at 2:34 PM, Valentino, Stephen <svalentino AT bnl.gov> wrote:
>
> Hi Gerard,
>
> Thanks.
> We'll order the cable when we learn how many test cables are needed.
>
> Regards,
> Steve Valentino
> 631-344-4644
>
> -----Original Message-----
> From: Gerard Visser <gvisser AT indiana.edu>
> Sent: Tuesday, February 19, 2019 10:06 AM
> To: Valentino, Stephen <svalentino AT bnl.gov>; star-fst-l AT lists.bnl.gov
> Subject: Re: [Star-fst-l] Weekly FST meeting - 2/14/2019
>
> Hi Steve,
> My recommendation for low-cost off-the-shelf test cable is to use two
> of 3M #
> 3750/16 (Mouser stock:
> https://www.mouser.com/ProductDetail/3M-Electronic-Solutions-Division/3750-16-100?qs=sGAEpiMZZMvo3LfgFpQA%252bDC4PK3fYmXxYMejL%252bekg9o%3d
> ) and one of Belden # 5502FE (Mouser stock:
> https://www.mouser.com/ProductDetail/Belden-Wire-Cable/5502FE-008U1000?qs=sGAEpiMZZMs5%2f3jTaGtq4JmHLIbs6dVBTDx60e5r0YM%3d
> ).
> I guess the test cable set should be same length as real cable in
> real FST, but there may be some other constraints too. So with 100' cable
> you can probably make at least 4 test cable sets. I don't know how many
> might really be wanted for tests though; Zhenyu should better say about
> that and the length.
> For the connector for at the patchpanel, I'd pick some alternative D
> connector (preferably machined-pin type) that must be available at Mouser
> too.
> Sincerely,
>
> Gerard
>
>
> p.s. The cables above are both UL approved and are NEC type CL2 and CMR,
> respectively. So you shouldn't have any issues with using them at STAR.
>
>
> On 2/18/2019 4:15 PM, Gerard Visser wrote:
>> Hi Steve,
>> Can you remind me what is that mating connector on the board? Is it
>> D37F?
>> I'd suggest for test cables (at least) we can find some quality D
>> connector from
>> Conec at Digikey or Mouser easier and cheaper than Positronics one. Is the
>> IST
>> patchpanel schematic and BOM posted someplace on drupal? Maybe we should
>> start
>> an "FST drawings" page where everything can be posted in its most current
>> version for useful reference, right now I have to dig through the email
>> trails
>> it is potentially error-prone.
>> As to the wire guage I think we determined that 22 AWG was needed for
>> the
>> power wires (for IST; could be smaller for FST) and we thought that 28 AWG
>> was
>> small enough for the other wires.
>> I'll look for some off-the-shelf easily available cables to use for
>> the
>> test setup, as promised.
>>
>> Gerard
>>
>>
>> On 2/14/2019 11:43 AM, Valentino, Stephen wrote:
>>> Hi Gerard,
>>>
>>> I'd like to order the Positronic connectors for the test cables. How
>>> many
>>> test cables should we make?
>>>
>>> The IST documents indicate they used 20 gauge pins in the Inner cable
>>> connector (PP end), but the wire used is 28 or 22 gauge. Do you remember
>>> why
>>> this was done?
>>>
>>> Regards,
>>> Steve Valentino
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
[Star-fst-l] Weekly FST meeting - 2/14/2019,
Ye, Zhenyu, 02/13/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/14/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Valentino, Stephen, 02/14/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/18/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Valentino, Stephen, 02/19/2019
- Re: [Star-fst-l] Weekly FST meeting - 2/14/2019, Zhenyu Ye, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Valentino, Stephen, 02/19/2019
- Re: [Star-fst-l] Weekly FST meeting - 2/14/2019, Valentino, Stephen, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/18/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
LI YI, 02/15/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/18/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
董家宁, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/19/2019
- Re: [Star-fst-l] Weekly FST meeting - 2/14/2019, Valentino, Stephen, 02/22/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
董家宁, 02/19/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/18/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Valentino, Stephen, 02/14/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
LI YI, 02/15/2019
- Re: [Star-fst-l] Weekly FST meeting - 2/14/2019, Yi Yang, 02/17/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Zhenyu Ye, 02/18/2019
- Re: [Star-fst-l] Weekly FST meeting - 2/14/2019, Gerard Visser, 02/18/2019
-
Re: [Star-fst-l] Weekly FST meeting - 2/14/2019,
Gerard Visser, 02/14/2019
Archive powered by MHonArc 2.6.24.