Hi Zhenyu,
I'll try to look over all the various things I was supposed to have looked over by the time of the meeting.
In meanwhile, let me again ask if possible we can see a few pictures documenting that things really fit w/ the hybrid to T-board connectors when mounted (or simulated mounted) on the mechanical structure, I think this would be wise we see this before the v2.2 hybrid production. Of course if it is impossible to check this at this time deciding to proceed anyway may be necessary.
Similarly I think it would be advisable we get pedestals out of one of the existing hybrids if possible before ordering v2.2, but if that is infeasible I guess it is a small risk.

Gerard


On 11/5/2019 8:27 PM, Ye, Zhenyu wrote:
Dear all,

We will have a weekly FST meeting this Thursday 9am BNL time. The meeting
agenda and bluejeans info can be found at
https://drupal.star.bnl.gov/STAR/blog/yezhenyu/forward-silicon-tracker-weekly-meeting

1. Hybrid, T-board, Inner Signal Cable - Jianing, Gerard, Mike
2. Mechanical structure - Yi, Han-Sheng
3. Module Assembly at Fermilab - Zhenyu
4. BNL Test stand - Prithwish, Hu
5. Simulation - Te-Chuan, Krishan

I think we have to discuss any remaining issue if any and decide on the v2.2
hybrid production, which may delay the whole project. We should also hear the
status of mechanical structure from Yi. If there is anything else to
report/discuss, please let me know.

Best
Zhenyu
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l





Archive powered by MHonArc 2.6.24.

Top of Page