Meeting minutes:
Mechanical structure
NCKU received two full modules from EASTON. Still see bending with the outer
structure. EASTON will try to increase number of injection points further to
see if it helps.
NCKU Mech Engineering and at AIDC will survey the mechanical structure and
compare with design drawings
NCKU received Stainless steel cooling tube after leakage test from AIDC that
can fit into the structures but will check with AIDC to see if they can be
made better
Yi will discuss with ADIC about making fixtures to glue hybrids onto the
structure
Yi will send out document soon
Cooling system
Elke talked to Rahul about bringing MIT engineer (Jason) to BNL, inspecting
the IST cooling rack, and decide to whether doing it at BNL or shipping to MIT
Han-Sheng/Yi started testing soft tube with NOVEC at NCKU. Te-chuan will pass
a piece of soft tube to Rahul/Flemming. Need information about the radiation
hardness of the soft tubes
Hybrids, T-boards, Inner signal cables
Gerard verified the schematics of the new hybrids and v3.0 T-boards. Will
look into the layout
Jianing: waiting for Gerard’s verification before placing the PO for new
hybrids. it will take 3 weeks to get the new hybrids
Mike proposed a few changes to existing v2.1 T-boards to work with prototype
modules, waiting for Gerard’s verification before making the changes and
sending the T-boards out for cable assembly
Mike and Gerard will follow up on production cable choice
Module assembly at Fermilab
UIC received design drawings of fixtures and started making them. Got the
first piece made by the UIC machine shop and will bring it to Fermilab for
examination with CMM and compare with design drawings.
> On Nov 8, 2019, at 6:56 AM, Gerard Visser <gvisser AT indiana.edu> wrote:
>
> hi Yi,
> This looks indeed quite good I think. Thank you for documenting it.
> Sincerely,
>
> Gerard
>
>
> On 11/8/2019 7:42 AM, Yi Yang wrote:
>> Hi Gerard and all,
>> We have a look over the mechanical structure and the hybrid (v2.2). We
>> believe the current design should be fine.
>> Please find some pictures in the following link:
>> STAR_FST_MS_Pic_20191108.pdf
>> <https://drupal.star.bnl.gov/STAR/system/files/STAR_FST_MS_Pic_20191108.pdf>
>> Our T-board doesn't have the male connector on it, but the space should be
>> sufficient.
>> Cheers,
>> Yi
>> +++++++++++++++++++++++++++++++++++++++++++++++++++
>> Yi Yang, Associate Professor
>> Department of Physics
>> National Cheng Kung University
>> Tainan, 701 Taiwan
>> E-Mail: yiyang AT ncku.edu.tw <mailto:yiyang AT ncku.edu.tw>
>> Tel: +886-6-2757575 ext.65237
>> Fax: +886-6-2747995
>> Group Web:
>> https://urldefense.proofpoint.com/v2/url?u=http-3A__phys.ncku.edu.tw_-7Eyiyang&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=8ygAAI6gQzVe9hFCRdEAO5MwBJh2ID34fiwLpV3P1Xo&m=VhO9qtrFPXk9uvTepdjNy1f0zEXGpjWzD0PZfiuO3M4&s=9JXh3_eWzL-6AWE74aObP6490RF0SjhFmoELQB6NhcM&e=
>> +++++++++++++++++++++++++++++++++++++++++++++++++++
>> On Wed, Nov 6, 2019 at 10:22 AM Gerard Visser <gvisser AT indiana.edu
>> <mailto:gvisser AT indiana.edu>> wrote:
>> Hi Zhenyu,
>> I'll try to look over all the various things I was supposed to
>> have
>> looked over
>> by the time of the meeting.
>> In meanwhile, let me again ask if possible we can see a few
>> pictures
>> documenting that things really fit w/ the hybrid to T-board connectors
>> when
>> mounted (or simulated mounted) on the mechanical structure, I think
>> this would
>> be wise we see this before the v2.2 hybrid production. Of course if it
>> is
>> impossible to check this at this time deciding to proceed anyway may be
>> necessary.
>> Similarly I think it would be advisable we get pedestals out
>> of one
>> of the
>> existing hybrids if possible before ordering v2.2, but if that is
>> infeasible I
>> guess it is a small risk.
>> Gerard
>> On 11/5/2019 8:27 PM, Ye, Zhenyu wrote:
>> > Dear all,
>> >
>> > We will have a weekly FST meeting this Thursday 9am BNL time. The
>> meeting
>> agenda and bluejeans info can be found at
>> >
>>
>> https://drupal.star.bnl.gov/STAR/blog/yezhenyu/forward-silicon-tracker-weekly-meeting
>> >
>> > 1. Hybrid, T-board, Inner Signal Cable - Jianing, Gerard, Mike
>> > 2. Mechanical structure - Yi, Han-Sheng
>> > 3. Module Assembly at Fermilab - Zhenyu
>> > 4. BNL Test stand - Prithwish, Hu
>> > 5. Simulation - Te-Chuan, Krishan
>> >
>> > I think we have to discuss any remaining issue if any and decide on
>> the
>> v2.2 hybrid production, which may delay the whole project. We should
>> also
>> hear the status of mechanical structure from Yi. If there is anything
>> else
>> to report/discuss, please let me know.
>> >
>> > Best
>> > Zhenyu
>> > _______________________________________________
>> > Star-fst-l mailing list
>> > Star-fst-l AT lists.bnl.gov <mailto:Star-fst-l AT lists.bnl.gov>
>> > https://lists.bnl.gov/mailman/listinfo/star-fst-l
>> >
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov <mailto:Star-fst-l AT lists.bnl.gov>
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
[Star-fst-l] Weekly FST meeting - 11/7/2019,
Ye, Zhenyu, 11/05/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/05/2019
- Re: [Star-fst-l] Weekly FST meeting - 11/7/2019, Ye, Zhenyu, 11/05/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Ye, Zhenyu, 11/05/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/05/2019
- Re: [Star-fst-l] Weekly FST meeting - 11/7/2019, Ye, Zhenyu, 11/06/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/05/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Yi Yang, 11/08/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/08/2019
- Re: [Star-fst-l] Weekly FST meeting - 11/7/2019, Zhenyu Ye, 11/12/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/08/2019
- Re: [Star-fst-l] Weekly FST meeting - 11/7/2019, Ye, Zhenyu, 11/07/2019
- <Possible follow-up(s)>
- Re: [Star-fst-l] Weekly FST meeting - 11/7/2019, Prithwish Tribedy, 11/05/2019
-
Re: [Star-fst-l] Weekly FST meeting - 11/7/2019,
Gerard Visser, 11/05/2019
Archive powered by MHonArc 2.6.24.