Below are the list of things I think we may want to get pre-approval and the
responsible person. It would be good if we can collect all the info
(material, data sheets, flammability, anything else?) by the end of this
week. Please have the info summarized in slides/word document and upload to
https://drupal.star.bnl.gov/STAR/event/2020/08/24/star-forward-silicon-tracker-meeting/safety-pre-approval-materials
Maowu: hybrid, T-board
Michael/Gerard: inner signal cable, connectors
Yi: flexible cooling tubs, mechanical structure, hybrid and MS gluing and
thermal grease
Zhenyu: glue/encapsulate used for APV and silicon sensor assembly
If I miss anything, please let me know.
Thanks,
Zhenyu
On
https://drupal.star.bnl.gov/STAR/event/2020/08/24/star-forward-silicon-tracker-meeting/safety-pre-approval-materials
attachment you can find the IST slides for safety review that Flemming found.
What we are trying to now is not safety review so not exactly the same.
> On Aug 19, 2020, at 10:54 PM, Aschenauer Elke-Caroline <elke AT bnl.gov> wrote:
>
> Zhenyu,
>
> for sure making sure all is compliant with safety is a good idea, but I
> think I would start with a list of things we use and pass it on to the
> safety committee and ask they see any issues. I think we do not need a
> review. If there are issues we deal with it. I personally think there
> should be none.
> Also this would be again more work on Rahul, and he is already overloaded.
>
> Cheers elke
>
>> On Aug 19, 2020, at 22:56, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
>>
>> Dear all,
>>
>> As the production starts ramping up, I think we should try to conduct a
>> safety review asap to get pre-approval of components/materials that will
>> be used in the detector module production soon. These would include all
>> the materials to make the detector modules, especially Chroming used to
>> coat the cooling tubes, glue/thermal grease used for hybrid/MS assembly at
>> NCKU in the next few weeks. We can also include the materials used for
>> APV/Silicon sensor assembly as well.
>>
>> Shall we also include the other things, such as the T-board, cable,
>> cooling tubes?
>>
>> Zhenyu
>>
>>> On Jul 31, 2020, at 8:20 AM, Gerard Visser <gvisser AT indiana.edu> wrote:
>>>
>>> hi Zhenyu,
>>> I believe someone from BNL from the project (Rahul? Flemming?) needs
>>> to consult with the appropriate safety officers to get advanced clearance
>>> of anything doubtful in the design, before production. This is how it
>>> went for instance with the custom cables used in IST and SSD - the cables
>>> were not official rated cables, rather only "by design similar" to such,
>>> and we submitted the documentation and samples _before_ detector
>>> production (but of course, after cable production, which was an
>>> investment that had to come first) for approval. The documents were
>>> examined, I believe at least one of the cables was given a burn test at
>>> BNL, and we got approval to use. Then in the safety review before
>>> installation we just referenced that approval and no problems. There was
>>> a similar pre=approval process for the Wiener MPOD power supplies, taken
>>> care of in the time of FGT detector construction.
>>> Flemming could correct this, but I don't believe such actual safety
>>> approval is within the scope of this review or committee. But a plan to
>>> get approval where needed, must be.
>>> Sincerely,
>>>
>>> Gerard
>>>
>>>
>>> On 7/31/2020 9:10 AM, Ye, Zhenyu wrote:
>>>> I don’t know when the safety review will take place, but we certainly
>>>> need the ES&H clearance before the actual production starts, because we
>>>> can’t have all the modules produced and then learn some of them do not
>>>> meet the requirement.
>>> _______________________________________________
>>> Star-fst-l mailing list
>>> Star-fst-l AT lists.bnl.gov
>>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>>
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>
>
> ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-
> ) `\ +
> / '. | Elke-Caroline Aschenauer (she/her/hers) =
> | `, -
> \,_ `-/ Brookhaven National Lab +
> ,&&&&&V Physics Dept., 25 Corona Road =
> ,&&&&&&&&: Bldg. 510 /2-195 Rocky Point, NY, -
> ,&&&&&&&&&&; 20 Pennsylvania Avenue 11778 +
> | |&&&&&&&;\ Upton, NY 11973 =
> | | :_) _ Tel.: 001-631-344-4769 Tel.: +1-631-569-4290 -
> | | ;--' | Cell-USA: +1-757-2565224 +
> '--' `-.--. | Cell-Europe: +49152220025211 =
> \_ | |—‘ -
> `-._\__/ Mail: elke AT bnl.gov elke.caroline AT me.com +
>
> +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=
>
>
>
>
>
>
>
>
>
-
[Star-fst-l] Safety review before module production,
Ye, Zhenyu, 08/19/2020
-
Re: [Star-fst-l] Safety review before module production,
Aschenauer Elke-Caroline, 08/19/2020
-
Re: [Star-fst-l] Safety review before module production,
Ye, Zhenyu, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Gerard Visser, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Zhenyu Ye, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Gerard Visser, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Zhenyu Ye, 08/26/2020
- Re: [Star-fst-l] Safety review before module production, Capotosto, Michael, 08/26/2020
- Re: [Star-fst-l] Safety review before module production, Zhenyu Ye, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Zhenyu Ye, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Gerard Visser, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Zhenyu Ye, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Gerard Visser, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Ye, Zhenyu, 08/26/2020
-
Re: [Star-fst-l] Safety review before module production,
Aschenauer Elke-Caroline, 08/19/2020
Archive powered by MHonArc 2.6.24.