  • Subject: Re: [[Star-tpc-l] ] [[Star-ops-l] ] Shutdown Operations Meeting and Schedule
  • Date: Mon, 14 Oct 2024 14:37:45 -0400

Dear Prashanth,
I think this amount of time for tpc maintenance needs to be discussed further. What you have is nominal 2 months, but with Thanksgiving and Christmas it is at least 2 weeks shorter. I suggest we have a meeting which includes Tonko, Tim, Alexi to discuss a more detailed planning. There was substantial damage to the electronics from the pp run that has to be addressed to have a successful Au-Au run

best Flemming




On 2024-10-14 14:15, Shanmuganathan, Prashanth wrote:
Dear all,
I would like to start the shutdown operations meetings from Thursday,
October 17th at 2:00 PM, during our usual time. Please use the regular
STAR ops meeting coordinates provided below.
The shutdown will officially begin at 8:00 AM on Monday, October
21st. We will have Greg available for technical assistance throughout
the week of 21st, and Bob will assist with magnet water draining and
pole tip removal.
Schedule of Operations:

*
On 21st, once the beam is dumped and the necessary pedestal runs are
completed, the shift crew will bring the detectors to APEX mode.

* The magnet will be ramped down, and Prashanth will remove the
magnet key.
* Subsystem experts will safely shut down their respective equipment
for the extended shutdown.

*
After the magnet is ramped down, Greg will remove the ground straps
and barriers around the magnet. This task should take approximately
one hour.
*
Akio will remove the BBC on Monday morning.
*
The EPD crew will remove the EPD on Monday, with plans to finish
within the day. To accommodate this, we will perform tasks 2, 3, and 4
in parallel where feasible.
*
Alexei will purge the TPC, TOF, MTD, and GMT subsystems. The shift
crew will remain on-site until Alexei provides clearance to dismiss.
*
Prashanth and David will purge the sTGC gas system, aligned with the
TPC purge timeframe.

*
Tim will remove the sTGC ROB box from the west pole tip between
Monday(21st) and Wednesday(23rd). Prashanth removes sTGC HV cables.
*
STSG and CAD MTechs will drain the magnet water and blow out the coils
on Wednesday(23rd). In the morning Jameela will coordinate with CAS
and water group to shutdown the magnet water.
*
STSG and CAD MTechs will remove the east pole tip on Friday(25th) and
the west pole tip on Monday(28th).
*
STSG and carpenters will install the east and west scaffolding on
Tuesday(29th).

* TPC/iTPC maintenance will begin on Wednesday, October 30th, and is
expected to continue until the first week of January.
*
The shutdown is estimated to last 4 to 5 months, although this has not
been officially confirmed. If the shutdown is not significantly
extended, we will begin preparations for the next run in the second
week of January.

Please let me know if I have missed any items or any suggestions.
Thanks,
Prashanth

Join ZoomGov Meeting
https://bnl.zoomgov.com/j/1603605873?pwd=NVk1aWs2OW5yb01rTzNtODhiaUJtQT09

Meeting ID: 160 360 5873
Passcode: 110789

---

One tap mobile
+16692545252,,1603605873#,,,,*110789# US (San Jose)
+16469641167,,1603605873#,,,,*110789# US (US Spanish Line)

---

Dial by your location
• +1 669 254 5252 US (San Jose)
• +1 646 964 1167 US (US Spanish Line)
• +1 646 828 7666 US (New York)
• +1 415 449 4000 US (US Spanish Line)
• +1 551 285 1373 US (New Jersey)
• +1 669 216 1590 US (San Jose)

Meeting ID: 160 360 5873
Passcode: 110789

--
Flemming Videbaek
senior scientist, emeritus
videbaek @ bnl.gov