usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity
- From: Hal Evans <hgevans AT indiana.edu>
- To: Elliot Lipeles <lipeles AT hep.upenn.edu>
- Cc: Michael Tuts <tuts AT pmtuts.net>, "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity
- Date: Wed, 17 Jul 2019 11:11:26 -0400
No - the percentages are fine - it should be clear that they lead to integer numbers of boards. Thanks - Hal On 7/17/19 11:08 AM, Elliot Lipeles
wrote:
Do you want me to calculate board counts?
I assumed that scope contingency could be done a bit
rougher (?).
Elliot
On Wed, Jul 17, 2019 at 11:06
AM Hal Evans <hgevans AT indiana.edu> wrote:
Thanks Elliot, I'll correct to the exact numbers in the next version. That will make it easier to relate this to board counts. Cheers - Hal On
7/17/19 11:01 AM, Elliot Lipeles wrote:
On Tue, Jul 16, 2019
at 6:58 PM Michael Tuts <tuts AT pmtuts.net>
wrote:
Hi Hal,I looking at your sheet when updating the info for the PEP, I think there are a number of date errors? Descoping tab: * What I had previously updated when I asked the L2s to update the PEP was for Muon dates for reducing sMDTs of 12/2021, 5/2022, 9/2022, 1/2023 vs what you show as 12/2019, 5/2019(!), 9/2019(!), 1/2019(!). The other Muon dates are also clearly wrong 6/2019 and 3/2019. * Is the LAr decision date really 9/2019? * Elliot has supplied me with $1,600 cost for 2/3 TP + 1/3 RTM + 5/6 TFM -- you have a different cost and a different number of RTM boards (2/3) , so I am wondering which is correct * Also he gave me $1,300 cost for 1/3 TP + 0 RTM + 2/3 TFM vs yours which shows 1/3 TP + 1/3 RTM + 2/3 TFM -- which is correct? Cheers, Mike -----Original Message----- From: Usatlas-hllhc-l2deputymgmt-nsf-l <usatlas-hllhc-l2deputymgmt-nsf-l-bounces AT lists.bnl.gov> On Behalf Of Hal Evans Sent: Tuesday, July 16, 2019 9:21 AM To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity Hi all, I've compiled all of your scope contingency/opportunity numbers into the attached table. I made a few minor modifications. 1. Trigger: I included an additional Trigger Opportunity - updating the gFEX algorithms for Phase-2. 2. Opportunity Dates: some of these were given only at the granularity of a year. I updated those to MMM-YY format, choosing a date arbitrarily. Please have a look and let me know if I've made any mistakes. Having this all compiled together highlights the fact that we are very thin on Physics impact/motivation for the contingency/opportunities. I realize that this will be difficult, but we should really include some sort of discussion of how these decisions could affect ATLAS physics. This can be hand-wavy (but obviously the more quantitative the better). The point is to demonstrate that we've thought about this NSF requirement for scope contingency/opportunity. Please try to get me some input on this by Thursday. Thanks - Hal -- ^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v Hal Evans hgevans AT indiana.edu https://urldefense.proofpoint.com/v2/url?u=http-3A__pages.iu.edu_-7Ehgevans_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=Z0wuTxQYnTTMlYma4lGZlO3skeCGVBrGGurYkWbhJsJuG5HaY82rmCNSdFOV7C4Z&m=49gTTyvVBnKd4JHf2bt3xiChfuWQepSFBd7zL7jIRNs&s=j1948e9ANvzfc-_oDaKNVLPoNi3XU9wJdj48WpRgsjM&e= Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^ _______________________________________________ Usatlas-hllhc-l2deputymgmt-nsf-l mailing list Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l -- ^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v Hal Evans hgevans AT indiana.edu http://pages.iu.edu/~hgevans/ Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^ -- ^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v Hal Evans hgevans AT indiana.edu http://pages.iu.edu/~hgevans/ Tel: (812)856-3828 Fax: (812)855-5533 253 Swain Hall West Indiana University 727 E. Third St. Bloomington, IN 47405 v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^v^ |
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Hal Evans, 07/16/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity, Elliot Lipeles, 07/16/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Michael Tuts, 07/16/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Hal Evans, 07/17/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity, Michael Tuts, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Elliot Lipeles, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Hal Evans, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Elliot Lipeles, 07/17/2019
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity, Hal Evans, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Elliot Lipeles, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Hal Evans, 07/17/2019
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] scope contingency/opportunity,
Hal Evans, 07/17/2019
Archive powered by MHonArc 2.6.24.