Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] early risk simulation results

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Redlinger, George" <redlinge AT bnl.gov>
  • To: "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: "Bee, Chris" <Chris.Bee AT cern.ch>, "cjmey AT iu.edu" <cjmey AT iu.edu>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] early risk simulation results
  • Date: Thu, 10 Jun 2021 19:30:04 +0000

Hi All,

 

So as we just discussed in the meeting, I’m sending around the simulation results we have so far for Tile and Muons.  The tabs “Cost Range Analysis” and “Historical” give the high-level summary

 

Concerning how we present this material, docDB 876 is what we prepared for the FDR: https://atlas-hllhc.docdb.bnl.gov/0008/000876/004/risk_summary_NSF.20190815.xlsx.  Presumably each subsystem would show its piece of the table shown in the Summary tab.

 

We’ll probably have to discuss whether or not we want to show the historical evolution.

 

As mentioned, it takes about a day to run each subsystem so LAr and Trigger should be appearing in the next couple of days, hopefully.

 

               -George

 

Attachment: Risk_simulation_summary_NSF.02.xlsx