Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] To address a panel question...

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Stephanie Majewski <smajewsk AT uoregon.edu>, Thomas Schwarz <schwarzt AT umich.edu>
  • Cc: Michael Tuts <tuts AT pmtuts.net>, "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] To address a panel question...
  • Date: Mon, 16 Aug 2021 12:42:58 -0400


Hi,

Knowing NSF, I think it's important to be more precise. For example, HTT *demonstrator* boards "local" testing is pre-MREFC, integrated testing is MREFC.

Best,

Gustaaf

On 8/16/21 12:11 PM, Stephanie Majewski wrote:
Hi Mike,

For Trigger, the compact summary of pre-MREFC activities that were completed post-FDR is:

HTT hardware: TFM, RTM boards tested; TP board completed and tested
HTT firmware: first version of a common framework was prepared (US and international contributions integrated)
Global firmware: completed initial studies for trigger framework and algorithms

A note: the Global firmware pre-MREFC "initial studies" phase was completed for the framework and most algorithms before the MREFC start; the only pre-MREFC activities that crossed the boundary were the completion of the initial studies for the hadronic event reconstruction algorithm.

Thanks,

Stephanie & Jinlong


On Mon, Aug 16, 2021 at 6:41 AM Thomas Schwarz <schwarzt AT umich.edu <mailto:schwarzt AT umich.edu>> wrote:

Hi Mike,

sMDT - construction of tube and chamber production facilities at
both UM and MSU.  Both facilities have now passed site certification
and are currently making tubes/chambers.
TDC - first prototype successfully constructed and passed all
specifications.  PDR passed.
CSM - Made technology choice.  First prototype successfully
constructed and passed all specifications.  PDR passed.
L0MDT - First design and first hardware demonstrator for both
service and command module built.  Early versions of firmware,
including segment finding algorithm produced.

Hope that works.

Tom

===================
Tom Schwarz
Associate Professor
Department of Physics
University of Michigan
Office: 734-764-8941
Lab: 734-763-7805
schwarzt AT umich.edu <mailto:schwarzt AT umich.edu>
===================



On Fri, Aug 13, 2021 at 2:16 PM Michael Tuts <tuts AT pmtuts.net
<mailto:tuts AT pmtuts.net>> wrote:

Dear L2s,____

__ __

You heard that George Angeli wanted a better (and compact
summary) of the pre-MREFC activities that were completed post
FDR. I would propose to gather a few main bullets (not in
excruciating detail) from each of your subsystems for that
period and if you send them to me I will compile them in one
slide which I can show in my talk and send to George. It would
be helpful to have that by COB Monday at the latest (earlier is
better).____

__ __

Thanks, Mike____



_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
<mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>

https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l

<https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtqVGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$>

_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
<mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>

https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtqVGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$

<https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtqVGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$>



_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l


--
Gustaaf Brooijmans - Columbia University
@Columbia: (212) 854 4527; Nevis virtual phone: (914) 591 2804

Als sie mich holten,
gab es keinen mehr, der protestieren konnte.




Archive powered by MHonArc 2.6.24.

Top of Page