  • From: Michael Tuts <tuts AT pmtuts.net>
  • To: John Parsons <parsons AT nevis.columbia.edu>, Stephanie Majewski <smajewsk AT uoregon.edu>, Thomas Schwarz <schwarzt AT umich.edu>
  • Cc: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] To address a panel question...
  • Date: Mon, 16 Aug 2021 18:10:15 +0000

Thanks

-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Monday, August 16, 2021 12:56 PM
To: Stephanie Majewski <smajewsk AT uoregon.edu>; Thomas Schwarz
<schwarzt AT umich.edu>
Cc: Michael Tuts <tuts AT pmtuts.net>;
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] To address a panel question...


Hi Mike,

For LAr, here is the preMREFC info:

ADC - radiation test of COLUTAv3 ADC ASIC delayed from March 2020 to November
2020, after which we successfully held the PDR in December 2020

FEB2 - the ATLAS Specifications Verification Review (SVR) for the FEB2 was
successfully held in April 2020

BE Electronics - the layouts for the SRTM and SRTM tester board were
finalized in June 2020.

Regards,
John

On 8/16/21 12:11 PM, Stephanie Majewski wrote:
> Hi Mike,
>
> For Trigger, the compact summary of pre-MREFC activities that were
> completed post-FDR is:
>
> HTT hardware: TFM, RTM boards tested; TP board completed and tested
> HTT firmware: first version of a common framework was prepared (US and
> international contributions integrated) Global firmware: completed
> initial studies for trigger framework and algorithms
>
> A note: the Global firmware pre-MREFC "initial studies" phase was
> completed for the framework and most algorithms before the MREFC
> start; the only pre-MREFC activities that crossed the boundary were
> the completion of the initial studies for the hadronic event
> reconstruction algorithm.
>
> Thanks,
>
> Stephanie & Jinlong
>
>
> On Mon, Aug 16, 2021 at 6:41 AM Thomas Schwarz <schwarzt AT umich.edu
> <mailto:schwarzt AT umich.edu>> wrote:
>
> Hi Mike,
>
> sMDT - construction of tube and chamber production facilities at
> both UM and MSU.  Both facilities have now passed site certification
> and are currently making tubes/chambers.
> TDC - first prototype successfully constructed and passed all
> specifications.  PDR passed.
> CSM - Made technology choice.  First prototype successfully
> constructed and passed all specifications.  PDR passed.
> L0MDT - First design and first hardware demonstrator for both
> service and command module built.  Early versions of firmware,
> including segment finding algorithm produced.
>
> Hope that works.
>
> Tom
>
> ===================
> Tom Schwarz
> Associate Professor
> Department of Physics
> University of Michigan
> Office: 734-764-8941
> Lab: 734-763-7805
> schwarzt AT umich.edu <mailto:schwarzt AT umich.edu>
> ===================
>
>
>
> On Fri, Aug 13, 2021 at 2:16 PM Michael Tuts <tuts AT pmtuts.net
> <mailto:tuts AT pmtuts.net>> wrote:
>
> Dear L2s,____
>
> __ __
>
> You heard that George Angeli wanted a better (and compact
> summary) of the pre-MREFC activities that were completed post
> FDR. I would propose to gather a few main bullets (not in
> excruciating detail) from each of your subsystems for that
> period and if you send them to me I will compile them in one
> slide which I can show in my talk and send to George. It would
> be helpful to have that by COB Monday at the latest (earlier is
> better).____
>
> __ __
>
> Thanks, Mike____
>
>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>
> <https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/us
> atlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtq
> VGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>
> https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtqVGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$
>
> <https://urldefense.com/v3/__https://lists.bnl.gov/mailman/listinfo/us
> atlas-hllhc-l2deputymgmt-nsf-l__;!!C5qS4YX3!UcmAZi_oFyWWNjeNJpX9P9xZtq
> VGTgmDAycJ0lD-P42tYOqzG9G16h7Jk5M-UdaOado$>
>
>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-
> l
>

--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!T1qXYZUUNGbk8o3MSPhJEiIyZ450eiO4T68Bqw8CfhbS6cxVQ4mwJPwIc6eCFqj2m77eFjpDsStmsHIC8kX8dzJnsldw$


______________________________________________________________________




Archive powered by MHonArc 2.6.24.

Top of Page