Hello all,
Thanks for the fixes. Quick follow-up;
-6.5: while you wait for Joey you can remove the sentence from 6.5 (since all
other schedule variances are < 100k maybe just talking about 6.5.1 is enough)
-good to hear the TDC has been submitted!
-6.8, 6.8.2 and 6.8.4 are *still* missing
Thx
Gustaaf
> On Apr 22, 2022, at 1:22 PM, Gustaaf Brooijmans
> <gusbroo AT nevis.columbia.edu> wrote:
>
>
> Hello all,
>
> Thanks for filing (most) variance reports on time. This progress is much
> appreciated. A few comments:
>
> -6.4.2: “to both” is probably a copy-paste leftover and should probably be
> removed
>
> -6.5: "is due to delayed invoicing of production PCB lot.” => does that
> mean things aren’t accrued properly? (Also, 6.5.3 schedule variance is
> small, so maybe not actually worth talking about here?)
> -6.5.3: "The invoices for manufacturing have not yet appeared” => but have
> things been delivered? I guess since there is a positive cost variance.
> If so, this is a mistake in accruals…
>
> -6.6 is good
> -6.6.3: I’ll reiterate that on the TDC front, any statement like “will
> start in the next few months” has lost all credibility - hasn’t this been
> going on for almost a year now? How likely is it this will actually happen
> in the next few months?
> -6.6.5: only 7 months of remaining float? Does that include the LS3 delay?
>
> -6.8, 6.8.2 and 6.8.4 are missing
>
> Best,
>
> Gustaaf
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports,
Gustaaf Brooijmans, 04/22/2022
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports,
Gustaaf Brooijmans, 04/25/2022
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports,
Gustaaf Brooijmans, 04/26/2022
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports, Stephanie Majewski, 04/26/2022
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports,
Gustaaf Brooijmans, 04/26/2022
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports,
Gustaaf Brooijmans, 04/25/2022
Archive powered by MHonArc 2.6.24.