  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports
  • Date: Tue, 26 Apr 2022 07:31:43 -0400


Hello all,

Thanks for the updates.

6.5 is good now.

-6.8: the you write "start-start instead of finish-finish” I think you mean
"start-start instead of finish-start” no?

-6.8.2: I’m not sure what "There was an extended decision process which left
some task for the baseline program behind as it became clear they would not
be needed” means, but it doesn’t seem to be needed. I would suggest to
remove. I don’t think what’s written under impact statement is an impact
statement. I think we want something along the lines of “Since this part of
the project is complete, the $134k positive cost variance will remain.”

-6.8.4: How was the fix tracked? Did we do a BCP for this?

Thanks,

Gustaaf


> On Apr 25, 2022, at 9:15 AM, Gustaaf Brooijmans
> <gusbroo AT nevis.columbia.edu> wrote:
>
>
> Hello all,
>
> Thanks for the fixes. Quick follow-up;
>
> -6.5: while you wait for Joey you can remove the sentence from 6.5 (since
> all other schedule variances are < 100k maybe just talking about 6.5.1 is
> enough)
>
> -good to hear the TDC has been submitted!
>
> -6.8, 6.8.2 and 6.8.4 are *still* missing
>
> Thx
>
> Gustaaf
>
>> On Apr 22, 2022, at 1:22 PM, Gustaaf Brooijmans
>> <gusbroo AT nevis.columbia.edu> wrote:
>>
>>
>> Hello all,
>>
>> Thanks for filing (most) variance reports on time. This progress is much
>> appreciated. A few comments:
>>
>> -6.4.2: “to both” is probably a copy-paste leftover and should probably be
>> removed
>>
>> -6.5: "is due to delayed invoicing of production PCB lot.” => does that
>> mean things aren’t accrued properly? (Also, 6.5.3 schedule variance is
>> small, so maybe not actually worth talking about here?)
>> -6.5.3: "The invoices for manufacturing have not yet appeared” => but have
>> things been delivered? I guess since there is a positive cost variance.
>> If so, this is a mistake in accruals…
>>
>> -6.6 is good
>> -6.6.3: I’ll reiterate that on the TDC front, any statement like “will
>> start in the next few months” has lost all credibility - hasn’t this been
>> going on for almost a year now? How likely is it this will actually
>> happen in the next few months?
>> -6.6.5: only 7 months of remaining float? Does that include the LS3 delay?
>>
>> -6.8, 6.8.2 and 6.8.4 are missing
>>
>> Best,
>>
>> Gustaaf
>> _______________________________________________
>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>