  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] March variance reports
  • Date: Fri, 22 Apr 2022 14:22:04 +0200


Hello all,

Thanks for filing (most) variance reports on time. This progress is much
appreciated. A few comments:

-6.4.2: “to both” is probably a copy-paste leftover and should probably be
removed

-6.5: "is due to delayed invoicing of production PCB lot.” => does that mean
things aren’t accrued properly? (Also, 6.5.3 schedule variance is small, so
maybe not actually worth talking about here?)
-6.5.3: "The invoices for manufacturing have not yet appeared” => but have
things been delivered? I guess since there is a positive cost variance. If
so, this is a mistake in accruals…

-6.6 is good
-6.6.3: I’ll reiterate that on the TDC front, any statement like “will start
in the next few months” has lost all credibility - hasn’t this been going on
for almost a year now? How likely is it this will actually happen in the
next few months?
-6.6.5: only 7 months of remaining float? Does that include the LS3 delay?

-6.8, 6.8.2 and 6.8.4 are missing

Best,

Gustaaf