Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - [Usatlas-hllhc-l2deputymgmt-nsf-l] First risk simulation results

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: "Meyer, Chris" <cjmey AT iu.edu>
  • To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
  • Cc: "usatlas-hllhc-management-l AT lists.bnl.gov" <usatlas-hllhc-management-l AT lists.bnl.gov>
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] First risk simulation results
  • Date: Fri, 24 Feb 2023 00:30:14 +0000

Hi All,

I've attached the first version of the risk simulation results for the NSF director's review.

The NSF workbook is old enough that it doesn't contain the "For Presentation" tab found in more recent DOE reviews; I'll add this next, along with continuing general sanity checks of the results. In the meantime, the final tab in the workbook (Cost Range Analysis) is probably the best summary of the results to start digesting.

Cheers,
Chris

Attachment: 2023-02-nsf-dr-summary-v3.xlsx