Hi,

Thanks for having filed most of the VRs in time. A few comments:

-6.4, 6.4.1, 6.4.2 look good, approved
-6.4.3 looks good, except for the very last sentence, that says the CV has
remained flat, when in fact it went up by 50%… I unlocked this.

-6.5.4 is missing

-6.6: you’re again writing “the schedule variance is driven by… (xx% of
cost)…” please change that to “xx%” or “xx% of schedule” => I have unlocked
this
-6.6.3: the corrective action appears to refer to the old schedule variance.
It should be replace with “no corrective action needed.” I have unlocked
this.
-6.6.4, 6.6.5 look good, approved

-6.8 and 6.8.4 are missing
-6.8.3 looks good and I have approved

Best,