Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] June VRs

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • Cc: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [[Usatlas-hllhc-l2deputymgmt-nsf-l] ] June VRs
  • Date: Wed, 24 Jul 2024 09:03:47 -0400


Hello all,

A follow-up:

> -6.4.3 looks good, except for the very last sentence, that says the CV has
> remained flat, when in fact it went up by 50%… I unlocked this.

This still needs to be fixed.

>
> -6.5.4 is missing

It’s there now, but only the schedule variance. We also need a cost variance
report.

>
> -6.6: you’re again writing “the schedule variance is driven by… (xx% of
> cost)…” please change that to “xx%” or “xx% of schedule” => I have
> unlocked this
> -6.6.3: the corrective action appears to refer to the old schedule
> variance. It should be replace with “no corrective action needed.” I have
> unlocked this

These need to be resubmitted.

>