[Sphenix-magnet-l] Brief Summary of sPHENIX Magnet Biweekly meeting (Feb. 3, 2016)
- From: Kin Yip <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] Brief Summary of sPHENIX Magnet Biweekly meeting (Feb. 3, 2016)
- Date: Wed, 3 Feb 2016 16:35:02 -0500
1. Roberto has expected that we'll do the pressure test/leak check tomorrow (Thursday, Feb. 4, 2016).
2. Dave Phillips has got the technicians to anchor the power supply/DAQ racks properly. But he doesn't like
the rubber "barrier" that his technicians have placed around the power-lead in the valve box. Because it's
not electrical-rated. He's ordering/getting one. In the meantime, I went to Mel VanEssendeft and asked
him to write in the work-permit that it's enough to disallow people from going up the platform. So that we
can proceed to hypot test without finishing this item of the ASSRC/ESRC checkoff list.
3. If the Cryo group can finish the pressure test on Thursday, Piyush/Sonny will do the hypot/impulse test on Friday.
4. They'll do the 2nd welding for the pipeline cut away from the ERL system today and this would finish this cutting/welding
business.
5. DAQ is basically ready. Piyush can turn on the DAQ logging system on Monday, possibly at the rate of every 10 minutes.
6. Achim has installed the physical Hall probe system inside the Solenoid. It's understood that he plans to measure the field
at the beginning of each current ramp (100 A) and at the end of each ramp.
7. In principle, everything is ready next week except Pat Talty (Cryo group), the software engineer, setting up/testing the
controlled cool-down. Apparently, he's the only person who can do the job and CeC wants to cool down as soon as possible
and he's still working in CeC. We're also try to cool-down and do our test as soon as possible.
Optimistically, Pat may come to help us on Wed. and very optimistically, we may start cooling down on Feb. 12.
[ Addendum:
8. We have had the ASSRC/ESRC safety walkthrough at 2:30 pm after our meeting. There is no real major item that I can remember.
We'll get a list of a few reminders (vaguely remembering that we have to administratively coordinate with the ATF II for the crane
movement during our test ... doing the final Magnet Review by Jesse Fite just before the low-power test). ]