Minutes shift change 2023-05-02
general
—————
- yesterday have submitted for approval to IRR, still with IRR: question regarding electrical connectors
- scaffolding boards have been painted on one side, now drying
- paint other side tomorrow (We)
- dry by Th evening
- plan was to put scaffolding back on Friday morning
- but now CAD wants to keep scaffolding out until BHSO approval: does not sound like a good idea to me b/c of indefinite time scale
- magnet inspection Fr 11-12
- liquid nitrogen will come Friday to fill dewar
access to bore wait list
———————————————
iHCal, EMCal, INTT, TPOT, MVTX (not available Friday)
evening: Genki
- busy shift
- four audio alarms, three of those triggered by EMCal dura chillers, low reservoir level
- contacted Joel and Lee
- solution at the time was to acknowledge with vision application (not obvious)
- Lee worked on a fix today
- fourth alarm racks 1W1, 1W2
- acknowledged
- couldn’t turn on 1W2
- breaker was off
- breaker was off
- according to Joel already off
night: Hanpu
- 5:00am TPC/TPOT coolant empty alarm
- outgoing shift crew confirmed not a serious problem
- 6:00am EMCal filter removed alarm
- acknowledged
- EMCal SiPM voltage question
- Cameron: will be updated in checklist
- Sean: currently still in expert mode
day: Sookhyun
- quiet morning
- 10:00am INTT work on 2W1 and 2W3 and bias testing North and South side
- 11:30am plug door test
- same chiller alarm, acknowledged
- tested audible INTT alarms
MBD (Abdul)
MBD (Abdul)
- finished HV GUI, will pass to shift crew soon
- Sal finished FEM boards
- plugged in FEM boards
- working on stabilizing laser time
HCal (Hanpu)
HCal (Hanpu)
- Dan Richford fixed sector 31, ch 5 which had no LED signal, changed backplane
- still need to check after we get HCal back from Martin
- Martin: tested what he was working on yesterday, not there yet, need another evening, hopefully will hand to Hanpu before his shift
Emcal (Sean)
- waiting for access to bore to fix channels
- Anthony working on bias voltage
- Rob working on insulating SiPM cooling lines
TPOT (John K)
- waiting for bore access
TPC (Jin)
- consistently taking pedestal data also with TPOT
- Takao updated automated FEE recovery
- Martin updated decoder, on github
- server updates, 24 GTM connections
- plan for next 24 h: expect operation in remote expert mode
- shift crew check usual safety items (like temperatures, flow rate)
INTT (Genki)
- interlock system upgraded filter system for bias
- tested, working
- debugged LV GUI
- waiting for rcdaq migration (in progress)
- interlocks not tested yet, not in hands of shift crew yet
MVTX (Cameron)
- rewiring flow switches for remote I/O monitor
- several flow switches active, others not
- flow rate has dropped to 1.5 l/m (alert: at 1.4 l/m)
- will reach out to manufacturer (stave cooling)
- investigating wiring of pressure sensors (4/6 stopped working)
- rack 2E1(currently yellow) hopefully back after that
- waiting for access
DAQ
- working on re-write of server that gives us access to DCM2s and partitioners
- unless you configure system every single time you are not able to start second run
- related to management of hold and busy
- will have self diagnostics
- Mickey and Dan L got Lvl1 to produce triggers from laser pulser
- Dan will try to read out laser data from forced accepts
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
- [Sphenix-run-l] Minutes shift change 2023-05-02, Stefan Bathe, 05/02/2023
Archive powered by MHonArc 2.6.24.